Planning application details ref: 1946 Carlow County Council

100%100% Complete (warning)

Planning Application: 1946 (Carlow County Council )
File Number: 1946
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 12/02/2019 Decision Due Date: 08/03/2020
Validated Date: 12/02/2019 Invalidated Date:
Further Info Requested: 05/04/2019 Further Info Received: 13/01/2020
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 06/03/2020
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By: 16/02/2020

Applicant Details

Applicant name: Elgin Energy Services Ltd.
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: for proposed works which will include a solar farm on an area of approximately 27.0 hectares, comprising photovoltaic panels on ground mounted frames, 1 No., onsite 38kV substation, an energy storage system (4 No. units), 10 No. single storey inverter/transformer stations, security fencing, a palisade double security gate, 2 No. storage containers, CCTV, a temporary construction stage wheelwash system and all ancillary development works. Elgin Energy Services Ltd are applying for the proposed solar farm to have planning permission that is effective for 10 years (and an operational period of 35 years). The planning application incudes a Natura Impact Statement
Development Address: Friarstown, Killerig, Co. Carlow
Architect Name: Location Key: FRIARSTOWN CARLOW
Electoral Division: Planner: Paula Murphy
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments: Article 33(3) Planning & Development Regulations 2001 (as amended)

Decision

Decision Date: 06/03/2020 Manager Order: 32825
Decision Type: Conditional Number of Conditions: 26
Grant Date: 04/06/2020 Grant Managers Order #: 32825
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 03/06/2030
Decision Description: for proposed works which will include a solar farm on an area of approximately 27.0 hectares, comprising photovoltaic panels on ground mounted frames, 1 no., onsite 38kV substation, an energy storage system (4 no. units), 10 no. single storey inverter/transformer stations, security fencing, a palisade double security gate, 2 no. storage containers, CCTV, a temporary construction stage wheelwash system and all ancillary development works. Elgin Energy Services Ltd are applying for the proposed solar farm to have planning permission that is effective for 10 years (and an operational period of 35 years). The planning application incudes a Natura Impact Statement

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: