Planning Application: 1274 (Clare County Council )
File Number:
1274
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
10/02/2012
Decision Due Date:
23/01/2013
Validated Date:
10/02/2012
Invalidated Date:
Further Info Requested:
03/04/2012
Further Info Received:
20/11/2012
Withdrawn Date:
Extend Date:
Decision Type:
Refused
Decision Date:
22/01/2013
Leave to Appeal:
Appeal Date:
15/02/2013
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
ESB Wind Development
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
for a 10 year Planning Permission for a Wind Farm Project at Moneypoint Generating Station. The development will consist of five wind turbines each having a rated electricity output of approximately 3,000 kilowatts, modification of the existing high voltage Electrical Transformer Station to house additional electrical equipment and an additional single-storey Control Building, two anemometer mastsand all associated site works, above and below ground. Each wind turbine will have an overall maximum dimension of 152 meters, comprising a tower 95 - 100 meters high, with a diameter of about 4 meters at the base, to which 3 blades of 52 - 55 meters length will be attached. An Environmental Impact Statement will be submitted to the Planning Authority with the Application.
Development Address:
Carrowdotia North and, Carrowdotia South, Killimer, Co Clare
Architect Name:
Location Key:
CARROWDOTIA KILRUSH
Electoral Division:
Planner:
Fiona Murren
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
EOT on FI up to and including 2 Jan 2013. BOX FILE
Decision
Decision Date:
22/01/2013
Manager Order:
67720
Decision Type:
Refused
Number of Conditions:
1
Grant Date:
12/12/2013
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
11/12/2023
Decision Description:
for a 10 year Planning Permission for a Wind Farm Project at Moneypoint Generating Station. The development will consist of five wind turbines each having a rated electricity output of approximately 3,000 kilowatts, modification of the existing high voltage Electrical Transformer Station to house additional electrical equipment and an additional single-storey Control Building, two anemometer mastsand all associated site works, above and below ground. Each wind turbine will have an overall maximum dimension of 152 meters, comprising a tower 95 - 100 meters high, with a diameter of about 4 meters at the base, to which 3 blades of 52 - 55 meters length will be attached. An Environmental Impact Statement will be submitted to the Planning Authority with the Application.