Planning Application: 1851856 (Donegal County Council )
File Number:
1851856
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
03/12/2018
Decision Due Date:
05/08/2019
Validated Date:
03/12/2018
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
01/02/2019
Decision Type:
Refused
Decision Date:
01/08/2019
Leave to Appeal:
Appeal Date:
22/08/2019
Commenced Date:
Submissions By:
15/01/2019
Applicant Details
Applicant name:
MR. TONY DOHERTY
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
A 10 YEAR PLANNING PERMISSION FOR A PROPOSED WIND TURBINE WITH A 30 YEAR OPERATIONAL LIFE FROM THE DATE OF COMMISSIONING. THE PROPOSED WIND TURBINE SITE WILL CONSIST OF 1 NO. THREE BLADED WIND TURBINE WITH A MAXIMUM BASE TO BLADE TIP HEIGHT OF UP TO 119.33 METRES AND WILL INCLUDE TURBINE TRANSFORMER, TURBINE BASE AND FOUNDATION, TURBINE HARDSTAND AND TEMPORARY SET-DOWN AREA, CONSTRUCTION OF NEW ACCESS TRACK, JUNCTION AND TURNING AREA, ON-SITE DRAINAGE MANAGEMENT WORKS , 1 NO. NEW SITE ENTRANCE WITHIN SORNE WIND FARM AND WITH ALL OTHER ANCILLARY AND ASSOCIATED DEVELOPMENT AND INFRASTRUCTURE INCLUDING GENERAL AND EXCAVATION WORKS
Development Address:
MEENKEERAGH , BUNCRANA , LIFFORD PO , CO. DONEGAL
Architect Name:
Location Key:
MEENKEERAGH
Electoral Division:
Ballyshannon Rural
Planner:
None
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
01/08/2019
Manager Order:
2019PH1516
Decision Type:
Refused
Number of Conditions:
1
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
Decision Description:
A 10 YEAR PLANNING PERMISSION FOR A PROPOSED WIND TURBINE WITH A 30 YEAR OPERATIONAL LIFE FROM THE DATE OF COMMISSIONING. THE PROPOSED WIND TURBINE SITE WILL CONSIST OF 1 NO. THREE BLADED WIND TURBINE WITH A MAXIMUM BASE TO BLADE TIP HEIGHT OF UP TO 119.33 METRES AND WILL INCLUDE TURBINE TRANSFORMER, TURBINE BASE AND FOUNDATION, TURBINE HARDSTAND AND TEMPORARY SET-DOWN AREA, CONSTRUCTION OF NEW ACCESS TRACK, JUNCTION AND TURNING AREA, ON-SITE DRAINAGE MANAGEMENT WORKS , 1 NO. NEW SITE ENTRANCE WITHIN SORNE WIND FARM AND WITH ALL OTHER ANCILLARY AND ASSOCIATED DEVELOPMENT AND INFRASTRUCTURE INCLUDING GENERAL AND EXCAVATION WORKS
ERECTION OF WINDFARM COMPRISING OF 16 NO, V66 1.75 MW TURBINES, 60 METRE TOWER HEIGHT, 66 METRE ROTOR DIAMETER, SUB STATION AND ASSOCIATED SITE ACCESS ROADWAYS
ERECTION OF WINDFARM COMPRISING OF 16 NO. V66 1.75 MW TUBINES, 60 METRE TOWER HEIGHT, 66 METRE TOTOR DIAMETER, SUB STATION AND ASSOCIATED SITE ACCESS ROADWAYS
WINDFARM COMPRISING OF 16 NO. V66 1.75 MW TURBINES, 60 METRE TOWER HEIGHT, 66 METER ROTOR DIAMETER AND ASSOCIATED SITE ACCESS ROADWAYS ON A SITE OF 97.67 HECTACRES
No Environment Impact Assesments Associated with this Application