Planning Application: 13829 (Galway County Council )
File Number:
13829
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
06/08/2013
Decision Due Date:
15/02/2014
Validated Date:
06/08/2013
Invalidated Date:
Further Info Requested:
27/09/2013
Further Info Received:
13/12/2013
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
14/02/2014
Leave to Appeal:
Appeal Date:
10/03/2014
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Western Power Developments Ltd
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
for ten year planning permission for development of a wind farm consisting of the following elements: *Eleven (11) No. wind turbines (with a maximum blade tip height of up to 140.5m) and associated hardstand areas. *One permanent meteorological mast (up to 90m). *One 110kv substation including two buildings (6.1m in height) and associated electrical equipment. *Provision of a new site entrance including bridge crossing. *Provision of new and upgraded internal site service road, and all underground cabling and associated infrastructure. *Provision of peat deposition area.(Gross Floor Space 207 sqm)
Development Address:
Cnoc Raithni (Knockranny)
Architect Name:
Location Key:
CNOC RAITHNI (KNOCKRANNY), ARDDEROO
Electoral Division:
Planner:
Brenda O'Neill
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
u
Comments:
Decision
Decision Date:
14/02/2014
Manager Order:
Decision Type:
Conditional
Number of Conditions:
28
Grant Date:
20/01/2016
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
19/01/2021
Decision Description:
for ten year planning permission for development of a wind farm consisting of the following elements: *Eleven (11) No. wind turbines (with a maximum blade tip height of up to 140.5m) and associated hardstand areas. *One permanent meteorological mast (up to 90m). *One 110kv substation including two buildings (6.1m in height) and associated electrical equipment. *Provision of a new site entrance including bridge crossing. *Provision of new and upgraded internal site service road, and all underground cabling and associated infrastructure. *Provision of peat deposition area.(Gross Floor Space 207 sqm)