File Number: | 212192 | ||
Application Type: | PERMISSION | Planning Status: | APPLICATION FINALISED |
Received Date: | 24/11/2021 | Decision Due Date: | 14/04/2022 |
Validated Date: | 24/11/2021 | Invalidated Date: | |
Further Info Requested: | 27/01/2022 | Further Info Received: | 18/02/2022 |
Withdrawn Date: | Extend Date: | ||
Decision Type: | Conditional | Decision Date: | 13/04/2022 |
Leave to Appeal: | Appeal Date: | 10/05/2022 | |
Commenced Date: | Submissions By: |
Applicant Details |
|||
---|---|---|---|
Applicant name: | EP Energy Developments Ltd. | ||
Applicant Address: | |||
Phone Number: | Fax Number: | ||
Corresp. Address: |
Proposed Development |
|||
---|---|---|---|
Development Description: | for an Open Cycle Gas Turbine power plant (299MW) and associated infrastructure and buildings. The proposed development will include: Demolition of existing administration building, gatehouse, workshop, storage buildings (3no.) and car parking area; Installation of an Open Cycle Gas Turbine (OCGT) unit and associated plant (Including air intake, stack (40m high); main, auxiliary and ancillary transformers; fire wall; acoustic wall; electrical rooms; finfan coolers; skids (to include gas skid, distillate fuel skid, compressor cleaning skid, air drier skid, compressed air skid, lube oil skid, CO2 fire fighting skid); propane store; Continuous Emissions Monitoring System (CEMS); fire water tank and pump house; hardstanding maintenance area]; Secondary fuel storage area [4 no. bunded distillate fuel storage tanks - each tank c. 20.2m high (incl. hand rail), 10m diameter]; Fuel forwarding building; Extension to existing distillate unloading plant [1 no. new pump house to be installed]; Fuel forwarding gantry; Expanded Above Ground Installation ('AGI') to facilitate connection to existing gas pipeline; A new 220 kV bay and 220kV bus section within the existing electricity substation; New administration building, gatehouse and associated car parking (2 no. spaces), workshop, storage buildings (3 no.) and car park (52 no. spaces); And all associated ancillary development, site works and services including fill, underground pipework and cabling , upgraded wastewater treatment plant, drainage infrastructure, lighting, fencing, internal roadways, vehicle and pedestrian access gates, vehicular ramp, entrance barrier, etc. The application relates to development for the purposes of an activity requiring a license from the Environmental Protection Agency under the Industrial Emissions Directive. It also relates to a Lower Tier COMAH establishment and therefore falls under the requirements of the Control of Major Accident Hazard (COMAH) Regulations, 2015. An Environmental Impact Assessment Report (EIAR) will be submitted to the planning authority with the application. | ||
Development Address: | Derryfrench | ||
Architect Name: | Location Key: | DERRYFRENCH TYNAGH | |
Electoral Division: | Planner: | EIMEAR O'DOHERTY | |
Social Housing Exempt: | Plan Enforcement #: | ||
IPC Licence Required: | No | Waste Licence Required: | No |
Protected Structure: | No | Protected Structure #: | |
Development Name: |
Comments |
|||
---|---|---|---|
Significant Case Flag: | 8 | Comments: | 8 & U |
Decision |
|||
---|---|---|---|
Decision Date: | 13/04/2022 | Manager Order: | |
Decision Type: | Conditional | Number of Conditions: | 27 |
Grant Date: | 08/02/2023 | Grant Managers Order #: | |
Section 47 Apply?: | Part 5 Apply?: | ||
Expiry Date: | 07/02/2028 | ||
Decision Description: | for an Open Cycle Gas Turbine power plant (299MW) and associated infrastructure and buildings. The proposed development will include: Demolition of existing administration building, gatehouse, workshop, storage buildings (3no.) and car parking area; Installation of an Open Cycle Gas Turbine (OCGT) unit and associated plant (Including air intake, stack (40m high); main, auxiliary and ancillary transformers; fire wall; acoustic wall; electrical rooms; finfan coolers; skids (to include gas skid, distillate fuel skid, compressor cleaning skid, air drier skid, compressed air skid, lube oil skid, CO2 fire fighting skid); propane store; Continuous Emissions Monitoring System (CEMS); fire water tank and pump house; hardstanding maintenance area]; Secondary fuel storage area [4 no. bunded distillate fuel storage tanks - each tank c. 20.2m high (incl. hand rail), 10m diameter]; Fuel forwarding building; Extension to existing distillate unloading plant [1 no. new pump house to be installed]; Fuel forwarding gantry; Expanded Above Ground Installation ('AGI') to facilitate connection to existing gas pipeline; A new 220 kV bay and 220kV bus section within the existing electricity substation; New administration building, gatehouse and associated car parking (2 no. spaces), workshop, storage buildings (3 no.) and car park (52 no. spaces); And all associated ancillary development, site works and services including fill, underground pipework and cabling , upgraded wastewater treatment plant, drainage infrastructure, lighting, fencing, internal roadways, vehicle and pedestrian access gates, vehicular ramp, entrance barrier, etc. The application relates to development for the purposes of an activity requiring a license from the Environmental Protection Agency under the Industrial Emissions Directive. It also relates to a Lower Tier COMAH establishment and therefore falls under the requirements of the Control of Major Accident Hazard (COMAH) Regulations, 2015. An Environmental Impact Assessment Report (EIAR) will be submitted to the planning authority with the application. |
Appeal Details | |||
---|---|---|---|
Notification Date: | 10/05/2022 | BP Reference #: | ABP-313538-22 |
Appeal Type: | THIRD PARTY | File Forward Date: | |
Submission Due Date: | 06/06/2022 | Submission Sent Date: | |
Appeal Decision: | CONDITIONAL | Decision Date: | 08/02/2023 |
Withdrawn Date: | Dismissed Date: | ||
Reason: | 14 |