Planning Application: 11300014 (Kildare County Council )
File Number:
11300014
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
05/07/2011
Decision Due Date:
25/09/2011
Validated Date:
05/07/2011
Invalidated Date:
Further Info Requested:
18/08/2011
Further Info Received:
29/08/2011
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
23/09/2011
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Atlantic Industries T/A Athy International Concentrates
Applicant Address:
Phone Number:
Fax Number:
016609099
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
Const of a new surface water drainage pipe and manholes, as well as an attenuation pond within the site near the north boundary. The new pipe will divert existing surface water to an axisting site surface water drain which discharges to the athy Town council surface water sewer. A new flow control device, in conjunction with the attenuation pond will limit the rate of discharge from the new surface water pipe. An oil separator will also be installed on the new surface water pipe.
Development Address:
Townspark Industrial Estate, Athy, Co. Kildare.
Architect Name:
Location Key:
TOWNSPARK INDUSTRIAL ESTATE
Electoral Division:
Planner:
None
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
23/09/2011
Manager Order:
2011/136
Decision Type:
Conditional
Number of Conditions:
14
Grant Date:
25/10/2011
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
24/10/2016
Decision Description:
Const of a new surface water drainage pipe and manholes, as well as an attenuation pond within the site near the north boundary. The new pipe will divert existing surface water to an axisting site surface water drain which discharges to the athy Town council surface water sewer. A new flow control device, in conjunction with the attenuation pond will limit the rate of discharge from the new surface water pipe. An oil separator will also be installed on the new surface water pipe.
American Fruits and Flavors Ireland DAC, Townparks Industrial Estate, Athy,
1. The demolition of an existing 9m high warehouse (1,770 sqm) and existing ancillary buildings (692 sqm) and infrastructure. 2. The construction of new two storey 14m high production building incorporating warehouse space, food process areas, loading and unloading facilities, staff offices and toilets, plant rooms, roof mounted solar panels, external elevation logo signage. The building has a gross floor area of 7,495 sqm over two floors (Ground floor 5,657 sqm and first floor area 1,838 sqm). 3. The demolition of an existing effluent treatment plant (144 sqm compound) and reconstruction of new treatment plant (952 sqm compound). 4. The installation of a sprinkler storage tank (113 sqm), a glycol tank (23 sqm) and construction of an associated pump house (41 sqm). 5. The installation of food and ethanol silos. 6. Construction of a new gated exit onto local road L8068 and security hut 6 sqm. 7. Construction of a new ESB substation and undergrounding of existing ESB power lines. 8. Amendments to the existing stormwater drainage system. 9. Provision of associated site infrastructure including electric vehicle parking spaces; cycle parking and shelter 20 sqm; tanker unloading bund; refrigeration and air conditioning plant and equipment; raised external plant deck (317 sqm); connections/upgrades to existing services; hard and soft landscaping; boundary treatments; external lighting and all other associated and ancillary development and works above and below ground level to complete the project. 10. Current operational hours of the entire facility are 7 a.m. to 4.30 p.m. It is proposed that the hours of operation would increase to 24 hours with the use of shifts. The facility will not be operational on Sundays or Bank holidays. This would apply to both the existing and the above proposed extension. 11. The planning application is accompanied by an Environmental Impact Assessment Report and a Natura Impact Assessment. Revised by Significant Further Information:
a) Changes to the design of the building including adjustments to the height of the building so it now ranges from 10m to 14.5m at its highest point;
b) Changes to the finishing and screening materials for the proposed building and associated infrastructure.
c) Revised plans illustrating items “a” and “b” including a “Materials” document illustrating the specification and location of the finishing materials and physical samples of the finishing materials proposed on the façade of the redesigned building.
d) Revised design of exit gate to include a new timber gate and revised piers and walls;
e) Revised site plan showing 3m wide footpath, public lighting and ducting;
f) Updated plan showing greater detail and dimensions of the electric vehicle parking spaces;
g) A revised Landscape Plan illustrating additional mitigating planting; a Landscape Design Rationale statement; and, a Landscape Maintenance and Management Specification report;
h) Addendum to the Environmental Impact Assessment Report (EIAR) and Addendum to the Non-Technical Summary of EIAR. Accompanying the EIAR Addendum is a separate booklet containing amended and new Landscape and Visual Photomontages of the revised extension design.
i) An Invasive Species Survey;
j) An Urban Design Statement to support and explain the design changes;
k) An updated Architectural Heritage Impact Assessment;
l) RFI Cover Report with responses to the various Further Information items; and,
m) Details of the locations of hot rolled asphalt (HRA) on adjoining public roads are contained in the RFI Cover Report;
No Environment Impact Assesments Associated with this Application