Planning Application: 171494 (Kildare County Council )
File Number:
171494
Application Type:
PERMISSION
Planning Status:
WITHDRAWN
Received Date:
22/12/2017
Decision Due Date:
Validated Date:
22/12/2017
Invalidated Date:
Further Info Requested:
23/02/2018
Further Info Received:
31/08/2018
Withdrawn Date:
21/11/2018
Extend Date:
Decision Type:
Decision Date:
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
BNRGN Hortland Limited,
Applicant Address:
Phone Number:
Fax Number:
24194960/24194961
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
for a period of 10 years to construct and complete a Solar PV Energy development with a total site area of 16.08 hectares, to include a single storey electrical substation building, electrical transformer and inverter station modules, solar PV panels ground mounted on support structures, vehicular access and internal access tracks, security fencing, electrical cabling and ducting, CCTV and other ancillary infrastructure, drainage, additional landscaping and habitat enhancement as required and associated site development works and services at a site
Permission for a period of 10 years to construct and complete a Solar PV Energy development with a total site area of 38.08 hectares, to include two electrical substation buildings, six electrical transformer and inverter station modules, solar PV panels ground mounted on support structures, vehicular access, access gates and internal access tracks, one spare parts container, security fencing, electrical cabling and ducting, CCTV cameras and other ancillary infrastructure, drainage, temporary construction compound, landscaping and habitat enhancement as required and associated site development works and services. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the Application
Townlands of Hortland and Knockanally, Donadea, Naas,
permission for a period of 10 years to construct and complete a Solar PV Energy development with a total site area of 38.08 hectares, to include two electrical substation buildings, six electrical transformer and inverter station modules, solar PV panels ground mounted on support structures, vehicular access, access gates and internal access tracks, one spare parts container, security fencing, electrical cabling and ducting, CCTV cameras and other ancillary infrastructure, drainage, temporary construction compound, landscaping and habitat enhancement as required and associated site development works and services. A Natura Impact Statement (NIS) will be submitted to the planning Authority with the application at a site
No Environment Impact Assesments Associated with this Application