Planning application details ref: 20543 Kildare County Council

100%100% Complete (warning)

Planning Application: 20543 (Kildare County Council )
File Number: 20543
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 29/05/2020 Decision Due Date: 28/09/2020
Validated Date: 29/05/2020 Invalidated Date:
Further Info Requested: 22/07/2020 Further Info Received: 01/09/2020
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 22/09/2020
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By:

Applicant Details

Applicant name: Renewable Energy Systems (RES)
Applicant Address:
Phone Number: Fax Number: 23945690
Corresp. Address:

Applicant Details


Proposed Development

Development Description: to amend application 18/94 at Ovidstown, Ballyvoneen, Enfield, Co. Kildare. The development will consist of a ground mounted solar photovoltaic (PV) farm to generate renewable electricity on a 13.6ha site and to extend the consent to 35 years, which comprises an access gate, security fencing, solar arrays and racking system, 2 no. electricity substations, grid connection building, temporary construction compound, CCTV cabling, hardstanding, new access track and ecologically beneficial landscape works
Development Address: Ovidstown,, Ballyvoneen,, Enfield,, Co. Kildare.
Architect Name: Daniel Kwarciany Location Key: ENFIELD
Electoral Division: Planner: Sandra McCormack
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 22/09/2020 Manager Order: DO30280
Decision Type: Conditional Number of Conditions: 5
Grant Date: 29/10/2020 Grant Managers Order #: DO30280
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 26/02/2024
Decision Description: to amend application 18/94 at Ovidstown, Ballyvoneen, Enfield, Co. Kildare. The development will consist of a ground mounted solar photovoltaic (PV) farm to generate renewable electricity on a 13.6ha site and to extend the consent to 35 years, which comprises an access gate, security fencing, solar arrays and racking system, 2 no. electricity substations, grid connection building, temporary construction compound, CCTV cabling, hardstanding, new access track and ecologically beneficial landscape works

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: