Planning Application: 211051 (Kildare County Council )
File Number:
211051
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
19/07/2021
Decision Due Date:
12/09/2021
Validated Date:
19/07/2021
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
06/09/2021
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
22/08/2021
Applicant Details
Applicant name:
Boards of Management, St. Conleth's Infant Primary School and St. Conleth & Mary's N.S
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
An additional storey extension to the previously approved single storey (Ref. No. 17/328) Autism Spectrum Disorder (ASD) Building, providing 1 No. Special Needs Classroom and associated spaces, with a floor area of 370 sqm. Layout reconfiguration to the existing boiler and Staff Room, alterations including demolition of boiler chimney and rebuild of the existing dividing wall and all associated site works
Development Address:
St. Conleth's Infant Primary School,, St. Conleth & Mary's National School,, Naas Road, , Newbridge, Co. Kildare.
Architect Name:
Adrian Sweeney - TODD Architects
Location Key:
NAAS ROAD, NEWBRIDGE
Electoral Division:
Planner:
Sarah O'Mahony
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
06/09/2021
Manager Order:
DO35514
Decision Type:
Conditional
Number of Conditions:
11
Grant Date:
19/10/2021
Grant Managers Order #:
DO35514
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
18/10/2026
Decision Description:
An additional storey extension to the previously approved single storey (Ref. No. 17/328) Autism Spectrum Disorder (ASD) Building, providing 1 No. Special Needs Classroom and associated spaces, with a floor area of 370 sqm. Layout reconfiguration to the existing boiler and Staff Room, alterations including demolition of boiler chimney and rebuild of the existing dividing wall and all associated site works
Boards of Management St. Conleth’s Infant School & St Conleth & Mary’s Primary School
Naas Road Newbridge Co. Kildare
(a) 20 classroom temporary system buildings of part 1 and part 2 storeys, of 1,600sqm in area, to be removed on completion of the development. (b) the removal of existing single storey prefabricated structures of 992sqm on completion of the development. (c) the refurbishment and extension of the primary school will consist of:(a) new 2 storey building providing 9 no. classrooms and support spaces with floor area of 686sqm; (b) reconfiguration and refurbishment of 5 no. classrooms and associated support spaces in existing school building. (d) the refurbishment and extension of the infant school will consist of: (a) new 2 storey building providing 9 no. classrooms and support spaces with floor area of 531sqm; (b) new double height general purpose hall and support spaces with a floor area of 272sqm; (c) reconfiguration and refurbishment of 7 no. classrooms and associated spaces in existing school building (e) new special needs unit 1 storey extension, providing 3 no. special needs unit classrooms and associated spaces with a floor area of 649sqm and a new 1 storey link corridor, with a floor area of 47sqm. (f) external works will include 4 no. ballcourts 2,340sqm, 2 no. junior play areas of 860sqm, a secure hard and soft play area of 200sqm, a sensory garden of 100sqm, a total of 66 car park spaces, widening and associated works to the existing vehicular entrance, proposed new 7000mm wide opening in existing boundary wall to accommodate re-configured road/exit off main Naas Road R445 to the South/Eastern boundary of the site, new gates and associated site landscape works (g) Temporary construction/school entrance to the South/Eastern corner boundary of the site formed off main Naas Road R445 for the duration of the construction period. Reinstatement of the existing boundary wall once works are complete (h) All associated and ancillary site works on an overall site area of 1.95 hectares
No Environment Impact Assesments Associated with this Application