Planning Application: 16500 (Laois County Council )
File Number:
16500
Application Type:
PERMISSION
Planning Status:
APPEALED FINANCIAL
Received Date:
10/10/2016
Decision Due Date:
01/03/2017
Validated Date:
10/10/2016
Invalidated Date:
Further Info Requested:
29/11/2016
Further Info Received:
02/02/2017
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
23/02/2017
Leave to Appeal:
Appeal Date:
22/03/2017
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
JBM Solar Developments Limited
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
construct for 10 years a Solar PV Energy Development comprising installation of photovoltaic panels on ground mounted frames/ support structures; underground cabling and ducting; 2 no. invert/transformer station with 1 no. HV cabin; 1 no. communications and storage structure; 2 no. substations; perimeter (stock proof) security fencing (2m high, c. 7.43 hectares) CCTV security cameras; site access road, landscaping and all associated ancillary site development works. A temporary construction compound will also be provided
Development Address:
Rathleague, Portlaoise, Co. Laois
Architect Name:
Justin Farrelly
Location Key:
RATHLEAGUE PORTLAOISE
Electoral Division:
Planner:
David O'Hara
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
23/02/2017
Manager Order:
110
Decision Type:
Conditional
Number of Conditions:
20
Grant Date:
24/07/2017
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
23/07/2027
Decision Description:
construct for 10 years a Solar PV Energy Development comprising installation of photovoltaic panels on ground mounted frames/ support structures; underground cabling and ducting; 2 no. invert/transformer station with 1 no. HV cabin; 1 no. communications and storage structure; 2 no. substations; perimeter (stock proof) security fencing (2m high, c. 7.43 hectares) CCTV security cameras; site access road, landscaping and all associated ancillary site development works. A temporary construction compound will also be provided