File Number: | 2078 | ||
Application Type: | PERMISSION | Planning Status: | APPLICATION FINALISED |
Received Date: | 17/02/2020 | Decision Due Date: | 04/05/2021 |
Validated Date: | 17/02/2020 | Invalidated Date: | |
Further Info Requested: | 02/06/2020 | Further Info Received: | 10/03/2021 |
Withdrawn Date: | Extend Date: | ||
Decision Type: | Refused | Decision Date: | 30/04/2021 |
Leave to Appeal: | Appeal Date: | 26/05/2021 | |
Commenced Date: | Submissions By: |
Applicant Details |
|||
---|---|---|---|
Applicant name: | Statkraft Ireland Limited | ||
Applicant Address: | |||
Phone Number: | Fax Number: | ||
Corresp. Address: |
Proposed Development |
|||
---|---|---|---|
Development Description: | construct up to 8 no. wind turbines with a tip height of up to 185 metres and all associated foundations and hardstanding areas; 1 no. on-site electrical substation; 1 no. temporary construction compound; all associated underground electrical and communications cabling connecting the turbines to the proposed on-site electrical substation; provision of new site access tracks and upgrading of existing access tracks and associated drainage; erection of 1 no. permanent meteorological mast of up to 110m in heights; works to facilitate the delivery of turbines adjacent to the N80 within the townlands of Dernacart and Forest Upper to include the laying of temporary surfacing; tree felling; and all associated site development works, ancillary works and equipment. Permission is sought for a period of 10 years and an operational life of 30 years from the date of commissioning of the entire wind farm. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development. | ||
Development Address: | Townlands of Dernacart, Forest Upper & Forest Lower, Co. Laois | ||
Architect Name: | Colm SHeehan | Location Key: | DERNACART GEASHILL |
Electoral Division: | Planner: | Donal Kiely | |
Social Housing Exempt: | Plan Enforcement #: | ||
IPC Licence Required: | No | Waste Licence Required: | No |
Protected Structure: | No | Protected Structure #: | |
Development Name: |
Comments |
|||
---|---|---|---|
Significant Case Flag: | 9 | Comments: | The dates and timelines on this application may be affected by the Emergency Covid-19 legislation |
Decision |
|||
---|---|---|---|
Decision Date: | 30/04/2021 | Manager Order: | 280 |
Decision Type: | Refused | Number of Conditions: | 1 |
Grant Date: | Grant Managers Order #: | ||
Section 47 Apply?: | Part 5 Apply?: | ||
Expiry Date: | 02/01/2034 | ||
Decision Description: | construct up to 8 no. wind turbines with a tip height of up to 185 metres and all associated foundations and hardstanding areas; 1 no. on-site electrical substation; 1 no. temporary construction compound; all associated underground electrical and communications cabling connecting the turbines to the proposed on-site electrical substation; provision of new site access tracks and upgrading of existing access tracks and associated drainage; erection of 1 no. permanent meteorological mast of up to 110m in heights; works to facilitate the delivery of turbines adjacent to the N80 within the townlands of Dernacart and Forest Upper to include the laying of temporary surfacing; tree felling; and all associated site development works, ancillary works and equipment. Permission is sought for a period of 10 years and an operational life of 30 years from the date of commissioning of the entire wind farm. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development. |
Appeal Details | |||
---|---|---|---|
Notification Date: | 28/05/2021 | BP Reference #: | ABP-310312-21 |
Appeal Type: | APPLICANT | File Forward Date: | |
Submission Due Date: | 24/06/2021 | Submission Sent Date: | |
Appeal Decision: | CONDITIONAL | Decision Date: | 03/01/2024 |
Withdrawn Date: | Dismissed Date: | ||
Reason: |