Planning Application: 2020 (Leitrim County Council )
File Number:
2020
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
12/02/2020
Decision Due Date:
07/01/2021
Validated Date:
12/02/2020
Invalidated Date:
Further Info Requested:
01/04/2020
Further Info Received:
04/11/2020
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
22/12/2020
Leave to Appeal:
Appeal Date:
26/01/2021
Commenced Date:
Submissions By:
08/12/2020
Applicant Details
Applicant name:
Brookfield Renewable Ireland Ltd.
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
development consisting of the installation of battery arrays, located within container units (16 number units, each 30 m2 by c. 2.6m tall), a control building (c.160.5m2 by c. 6.4m tall), transformer (c.5m tall) and a new site entrance. the development will include for ancillary infrastructure including security fencing, lighting, CCTV, internal access roads and drainage. the overall development site is c. 0.44Ha. The application includes a Natura Impact Statement (NIS)
Development Address:
Corderry (E.D. Belhavel), Co. Leitrim
Architect Name:
Grainne Daly
Location Key:
CORDERRY, BELHAVEL
Electoral Division:
Planner:
Deirdre Lardner
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
22/12/2020
Manager Order:
Decision Type:
Conditional
Number of Conditions:
11
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
10/02/2027
Decision Description:
development consisting of the installation of battery arrays, located within container units (16 number units, each 30 m2 by c. 2.6m tall), a control building (c.160.5m2 by c. 6.4m tall), transformer (c.5m tall) and a new site entrance. the development will include for ancillary infrastructure including security fencing, lighting, CCTV, internal access roads and drainage. the overall development site is c. 0.44Ha. The application includes a Natura Impact Statement (NIS)