File No |
Staus |
Type |
Decision |
Received Date |
Name |
Development Address |
Description |
011363 |
APPLICATION FINALISED |
PERMISSION |
C |
14/11/2001 Wednesday |
College Proteins Ltd |
College College Road Nobber |
an increase in capacity of their meat rendering plant from a permitted 75000 tonnes per annum (reg ref 97/269) to 125,000 tonnes per annum & the construction of 4 No. tallow storage silos each with a capacity of 200 cubic metres to facilitate this increase in capacity. Permission is also sought for the retention of a bunded area for the proposed tallow tanks with an area of 210m2, a cooker room extension & store to the north western side of the main process building with a gross floor of 233m2, a laboratory building with a gross floor area of 24m2, an extension to the administration building to provide a canteen for employees with a gross floor area of 27.2m2, a DERV tank with a capacity of 35.6 cubic metres, a final effluent storage tank with a capacity of 290 cubic metres, a weighbridge & internal access road parallel to College Road, the relocation of the approved BBK Biofilter No 2 by 14m approximately to the north east, BBK Biofilters No 3 (floor area 106m2, 4 metres high) & 4 no. |
1313 |
APPLICATION FINALISED |
PERMISSION |
|
01/01/2018 Monday |
College Proteins |
College Road Nobber Co Meath |
Application made directly to An Bord Pleanala under Section 37E of the Planning and Development Act 2000, as amended, including and EIS by College Proteins, for Development at College Road, Nobber, Co Meath |
211221 |
APPLICATION FINALISED |
PERMISSION |
C |
23/06/2021 Wednesday |
College Proteins |
College Road College Nobber, Co. Meath |
planning permission to amend a permitted Biodiesel Manufacturing Facility (Meath County Council Reg. Ref. KA/160786; as amended by Reg. Ref. KA/180354), on a site of c. 0.62 hectares at College Road, College, Nobber, Co. Meath. The development will consist of the extension to the existing Biodiesel Manufacturing Facility across all 3 no. floor levels resulting in an increased floor area of c. 354sqm; the provision of an external stairs; the provision of an off-loading bund area and all ancillary site development works above and below ground. The application relates to development which comprises or is for purposes of an activity requiring an Industrial Pollution Prevention and Control Licence (now replaced by an Industrial Emissions Licence). |
22696 |
APPLICATION FINALISED |
PERMISSION |
C |
27/05/2022 Friday |
College Proteins |
College Proteins College Road, College Nobber, Co. Meath |
the provision of a maintenance workshop and a lorry wash either side of the existing garage and an associated internal access road; provision of a store extension and an amenity block/office extension to the existing engineering workshop; provision of a chemical store and 2 No. chemical storage tanks within bunded area; provision of a security building at the site entrance; car parking, and all associated site development and infrastructure. The application relates to development which comprises or is for the purposes of an activity requiring an Industrial Emissions Licence |
88402 |
APPLICATION FINALISED |
PERMISSION |
C |
11/05/1988 Wednesday |
John O'Rourke |
College, Nobber, Co. Meath |
constuction of buildings for the production of bonemeal and tallow from offal & clean bones & ancillary works |
89870 |
APPLICATION FINALISED |
PERMISSION |
C |
12/07/1989 Wednesday |
College Proteins Ltd |
College, Nobber, Co. Meath |
retention of plant rooms and ancilliary services |
97269 |
APPLICATION FINALISED |
PERMISSION |
C |
07/03/1997 Friday |
College Proteins Limited |
College & Rathgillan College Road Nobber, Co. Meath |
the retntion of 5 tallow tanks, a condenser, covered unloading area, chimney stack, bunding of storage tanks,aeration tank,effluent tank,DAF unit,retention & completion of foundations, road slab and drainagework,new works comprising a factory extensi |
KA20256 |
APPLICATION FINALISED |
PERMISSION |
C |
06/08/2002 Tuesday |
College Proteins Ltd. |
College Road College Nobber, Co. Meath |
construction of an extension to the existing main processing building for the provision of a second processing line which will process Class 1 and Class 2 animal by-products not intended for human consumption. Raw materials that come within Class 1 and 2 are defined by Com/2000 / 0574 Final - COD 2000 / 0259. This is proposed for a regulation of the European Parliament and of the Council. The extension will include an airlock reception area (120 sq. m.), a raw materials intake area (289 sq m) containing a raw materials intake hopper, primary and secondary crushers, a cooker which is to be moved from the existing processed building and all associated ancillary plant and machinery including pumps and pipe work. The extension to the existing main processing building also provides for an access corridor to connect the raw materials reception area to a new process building. The proposed new processing building (518 sq m) will be 16m in height over two floors. This process building |
KA70425 |
APPLICATION FINALISED |
PERMISSION |
C |
13/06/2007 Wednesday |
College Proteins |
College Road, College, Nobber, Co. Meath |
the retention of 4 no. existing structures on site including: a workshop building for the manufacture of plant and machinery, located to the west of the main process building (540 sq.m); a building for the maintenance of haulage vehicles, located to the east of the main process building (400 sq.m); a bio-filter structure to facilitate the control of odour, located to the east of the main process building (225 sq.m); and an ancillary storage building, located to the rear of the main office building (22sq.m). These structures are all single-storey and are used in connection with an on-going meat rendering operation |
KA160786 |
APPLICATION FINALISED |
PERMISSION |
C |
21/07/2016 Thursday |
College Proteins |
College Proteins College Road, Nobber Co. Meath |
the application site comprises an area of c.1.47 hectares. Permission is sought for the construction of a biodiesel manufacturing facility producing up to 25,000 tonnes of biodiesel per annum. The facility comprises: a process building (maximum height of c. 23m) of c. 3,284 sqm Gross Floor Area (GFA) and associated tank farm (consisting of 12 No. external storage tanks, cooling unit, fertiliser silo, loading/uploading station); weigh bridge; security building (c. 33 sqm GFA); 22 No. car parking spaces; 5 No. HGV parking spaces; overground pipe racks linking to the existing rendering plant and wastewater treatment plant; a pipe bridge linking the process building and tank farm; and all ancillary site development, landscaping and boundary treatment works above and below ground. The maximum height of the proposed development is the c. 25 m stack adjoining the column tower of the process building. The application relates to development which comprises or is for the purposes of an activity requiring an Industrial Pollution Prevention and Control Licence (now replaced by an Industrial Emissions Licence). An Environmental Impact Statement (EIS) will be submitted to the Planning Authority with the application |
KA180183 |
APPLICATION FINALISED |
EXTENTION OF DURATION |
U |
26/02/2018 Monday |
College Proteins |
College Rd. Nobber Co. Meath |
construction of a biomass combined heat and power (CHP) plant and associated ash landfill facility adjacent to the existing meat rendering plant on the College Proteins site, located in the townlands of College and Rathgillen. The application site extends approximatley 19.25 Hectares. The Biomass CHP plant, when operating at full capacity, will be capable of processing 105,000 tonnes of biomass per annum. the proposed CHP plant has been designed to process a maximum of 52,500 tonnes per annum of meat and bone meal (MBM) and 52,500 tonnes per annum of waste organic liquids (derived from the agriculture, food and drink industries). The plant will generate some eight megawatts of electricity and will provide a net export of six megawatts for use outside the plant. The CHP plant will be housed in a single building (3130 Square metres) designed with concrete and steel structural framework and covered in metal profiled cladding. This building will house an unloading bay and fuel reception area, a fluidised bed combustion (FBC) system, a boiler system, a turbine/alternator set, a fabric filter system, a service building and an office building. There will be an induced draught (ID) fan and a flue stack for emissions to atmosphere, approximatley 40 metres in height, located outside. The proposed development also provides for two pipe connections within the existing rendering facility and the CHP plant. The new plant facility will be located to the rear (south/west) of the existing industrial plant buildings on site. The proposed process building will be approximatley 96 metres in length, 36 metres in width with a ridge height of 18.4 metres. A separate metal profiled clad enclosure (490 Square metres) will house an air cooled condenser immediately adajacent to the main process building. The condenser structure will be 35 metres in length, 14 metres in width and 15.2 metres in height. The proposed ash landfill will be located in the south- western part of the application site and will be connected to the proposed process buildings by an internal access road measuring approximatley 100 metres in length. The landfill will cater for non hazardous bed ash generated in the combustion process. It will also comprise the following elements: construction of engineered dry storage ash cells. These cells will be constructed and filled one at a time; a landfill runoff water lagoon;a temporary soil desposition area, a separate weighbridge and control office (57 square metres) |
KA180354 |
APPLICATION FINALISED |
PERMISSION |
C |
12/04/2018 Thursday |
College Proteins |
College Road College, Nobber Co. Meath |
to amend a permitted Biodiesel Manufacturing Facility (Meath County Council Reg. Ref. KA/160786), on a site of 1.49 hectares. The development will consist of the reconfiguration of the process building and associated tank farm and the provision of a new gas electricity generation unit with heat recovery. The reconfiguration on site will consist of: A revised configuration of the process building, resulting in an increase of c.53 sqm in the gross floor area of the building from c. 3,284 sqm to c. 3,337 sqm. There is no increase in the overall height of the building; An increase in the footprint of the tank farm and number of external storage tanks from 12 no. to 21 no.; Amendments to the permitted drainage layout; The proposed amendments do not result in an increase in the overall permitted production of 25,000 tonnes of biodiesel per annum. The following works will be completed as enabling works (as permitted under Reg. Ref. KA/160786): Site access works, excavation works and gravel infill to allow for the provision of foundations for the permitted layout of the process building. The application relates to development which comprises or is for the purpose of an activity requiring an Industrial Pollution Prevention and Control Licence (now replaced by an Industrial Emissions Licence). An Environmental Impact Statement (now referred to as an Environmental Impact Assessment Report (EIAR) will be submitted to the Planning Authority with the application |
KA200727 |
APPLICATION FINALISED |
PERMISSION |
C |
11/06/2020 Thursday |
College Proteins |
College Road College Nobber, Co. Meath |
planning permission is sought for the following: A. Construct new 6 bay workshop extension to existing engineering workshop. B. Retain existing electrical panel room, together with carparking and site development works |