File Number: | 221632 | ||
Application Type: | PERMISSION | Planning Status: | APPLICATION FINALISED |
Received Date: | 14/12/2022 | Decision Due Date: | 16/02/2023 |
Validated Date: | 14/12/2022 | Invalidated Date: | |
Further Info Requested: | Further Info Received: | ||
Withdrawn Date: | Extend Date: | ||
Decision Type: | Conditional | Decision Date: | 15/02/2023 |
Leave to Appeal: | Appeal Date: | 14/03/2023 | |
Commenced Date: | Submissions By: | 26/01/2023 |
Applicant Details |
|||
---|---|---|---|
Applicant name: | Christopher Gibney and Local Power Ltd | ||
Applicant Address: | |||
Phone Number: | Fax Number: | ||
Corresp. Address: |
Proposed Development |
|||
---|---|---|---|
Development Description: | planning permission for the development of an Anaerobic Digestion Facility to produce renewable gas and electricity on a site of circa. 4.24 hectares at the townland of Curragh, Carnaross, Co. Meath. The development comprises storage and processing plant to accommodate agricultural manures, residues, slurries and grass silage and its conversion into a methane rich biogas that is a carbon negative alternative to natural gas, and a nutrient rich fertiliser, digestate. Carbon dioxide from the process will also be captured and converted into food grade CO2. The proposed supporting infrastructure to be developed includes inter alia, 1 no. combined primary and secondary digestion tank; 1 no. enclosed feedstock storage building; 1 no. enclosed silage clamp, 1 no. enclosed digestate separation building, (housing 1 no. screw press separator, 1 no. centrifugal separator & a digestate pit); 1 no. digestate treatment building; 1 no. digestate storage tank; 2 no. CHP units (2 x 500kW), biogas upgrading unit, gas grid entry unit, carbon dioxide capture equipment, gas flare, all other on site processing plant above and below ground, facility office and administration building, weighbridge, roof mounted solar arrays / photovoltaic panels, all associated car & vehicle parking, internal road layouts, all supporting plant, process and storage facilities will be housed on hard surfaced and bunded areas, all other above and below ground services, landscaping, palisade fencing and boundary treatments and a new access road from the R147 with an underground gas pipeline to the gas grid connection in the R147. The facility requires an Industrial Emissions License from the EPA and is accompanied by a Natura Impact Statement (NIS) and an Environmental Impact Assessment Report (EIAR) | ||
Development Address: | Curragh , Carnaross, Co. Meath | ||
Architect Name: | Oisin Doherty | Location Key: | CURRAGH |
Electoral Division: | Incorrect Icl Voter Recor | Planner: | Gerard Kellett |
Social Housing Exempt: | Plan Enforcement #: | ||
IPC Licence Required: | No | Waste Licence Required: | No |
Protected Structure: | No | Protected Structure #: | |
Development Name: |
Comments |
|||
---|---|---|---|
Significant Case Flag: | Comments: |
Decision |
|||
---|---|---|---|
Decision Date: | 15/02/2023 | Manager Order: | 228/23 |
Decision Type: | Conditional | Number of Conditions: | 15 |
Grant Date: | 02/05/2023 | Grant Managers Order #: | |
Section 47 Apply?: | Part 5 Apply?: | ||
Expiry Date: | 01/05/2028 | ||
Decision Description: | planning permission for the development of an Anaerobic Digestion Facility to produce renewable gas and electricity on a site of circa. 4.24 hectares at the townland of Curragh, Carnaross, Co. Meath. The development comprises storage and processing plant to accommodate agricultural manures, residues, slurries and grass silage and its conversion into a methane rich biogas that is a carbon negative alternative to natural gas, and a nutrient rich fertiliser, digestate. Carbon dioxide from the process will also be captured and converted into food grade CO2. The proposed supporting infrastructure to be developed includes inter alia, 1 no. combined primary and secondary digestion tank; 1 no. enclosed feedstock storage building; 1 no. enclosed silage clamp, 1 no. enclosed digestate separation building, (housing 1 no. screw press separator, 1 no. centrifugal separator & a digestate pit); 1 no. digestate treatment building; 1 no. digestate storage tank; 2 no. CHP units (2 x 500kW), biogas upgrading unit, gas grid entry unit, carbon dioxide capture equipment, gas flare, all other on site processing plant above and below ground, facility office and administration building, weighbridge, roof mounted solar arrays / photovoltaic panels, all associated car & vehicle parking, internal road layouts, all supporting plant, process and storage facilities will be housed on hard surfaced and bunded areas, all other above and below ground services, landscaping, palisade fencing and boundary treatments and a new access road from the R147 with an underground gas pipeline to the gas grid connection in the R147. The facility requires an Industrial Emissions License from the EPA and is accompanied by a Natura Impact Statement (NIS) and an Environmental Impact Assessment Report (EIAR) |
Appeal Details | |||
---|---|---|---|
Notification Date: | 15/03/2023 | BP Reference #: | ABP-316047-23 |
Appeal Type: | THIRD PARTY | File Forward Date: | 23/03/2023 |
Submission Due Date: | 11/04/2023 | Submission Sent Date: | 11/04/2023 |
Appeal Decision: | WITHDRAWN | Decision Date: | |
Withdrawn Date: | 26/04/2023 | Dismissed Date: | |
Reason: |