Planning application details ref: AA180383 Meath CoCo

100%100% Complete (warning)

Planning Application: AA180383 (Meath CoCo)
File Number: AA180383
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 20/04/2018 Decision Due Date: 14/06/2018
Validated Date: 20/04/2018 Invalidated Date:
Further Info Requested: Further Info Received:
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 07/06/2018
Leave to Appeal: Appeal Date: 05/07/2018
Commenced Date: Submissions By: 24/05/2018

Applicant Details

Applicant name: Power Capitable Renewable Energy Limited
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: a 10 year permission for development on lands in the townland of Irishtown, Kilbrew, Co. Meath. The development will consist of the construction of an up to 8.7 MW solar PV farm comprising approximately 27,800 no. photovoltaic panels on ground mounted frames within a site area of 10.82 hectares and associated ancillary development including 8 no. transformer stations, 8 no. auxiliary transfomer stations, 8 no. inverters, 1 no. single storey storage building, 1 no. single storey communications building, 1 no. single storey client building, 3 no. CCTV security cameras mounted on 4 metre high poles and perimeter security fencing (2 metres high);1 no. single storey client side substation (DNO) and 1 no. CCTV security camera mounted on a 4 metre high pole on a 0.04 hectare site on the eastern side of the landholding to the east of the area of the photovoltaic panels; the construction of a vehicular access from the adjoining L5003-44 road; and the construction of a hardcore access track between the area of the photovoltaic panels, the client side substation and the proposed road access point (0.19 hectares)
Development Address: Irishtown, Kibrew, Co. Meath
Architect Name: IMG Planning Limited Location Key: IRISHTOWN
Electoral Division: Incorrect Icl Voter Recor Planner: Billy Joe Padden
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 07/06/2018 Manager Order: A762/18
Decision Type: Conditional Number of Conditions: 33
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 17/04/2029
Decision Description: a 10 year permission for development on lands in the townland of Irishtown, Kilbrew, Co. Meath. The development will consist of the construction of an up to 8.7 MW solar PV farm comprising approximately 27,800 no. photovoltaic panels on ground mounted frames within a site area of 10.82 hectares and associated ancillary development including 8 no. transformer stations, 8 no. auxiliary transfomer stations, 8 no. inverters, 1 no. single storey storage building, 1 no. single storey communications building, 1 no. single storey client building, 3 no. CCTV security cameras mounted on 4 metre high poles and perimeter security fencing (2 metres high);1 no. single storey client side substation (DNO) and 1 no. CCTV security camera mounted on a 4 metre high pole on a 0.04 hectare site on the eastern side of the landholding to the east of the area of the photovoltaic panels; the construction of a vehicular access from the adjoining L5003-44 road; and the construction of a hardcore access track between the area of the photovoltaic panels, the client side substation and the proposed road access point (0.19 hectares)

Appeal Details


Appeal Details
Notification Date: 17/09/2018 BP Reference #: ABP-301990-18
Appeal Type: THIRD PARTY File Forward Date: 16/07/2018
Submission Due Date: 14/10/2018 Submission Sent Date: 12/10/2018
Appeal Decision: CONDITIONAL Decision Date: 18/04/2019
Withdrawn Date: Dismissed Date:
Reason: