1. demolish existing service station/garage buildings and dwelling. 2. Construct new service station shop building containing 100 sq.m retail area with ancillary food bar area of 70 sq.m with associated storage and ancillary facilities. 3. Install 4 no fuel dispensing islands. 4. Install forecourt canopy over fuel dispensing pump islands. 5. Install 3 no. 40,000 L underground fuel tanks. 6. Install 2 no. car wash pads and service area. 7. Construct a fenced ancillary area to include refuse holding area. 8. Install 2 no. main ID signs. Further information submitted in realtion to planning application DA/50475 in which the following amendments have been made; 1. Reduction of 2. No. car wash pads to 1 No. car wash pad with splash screens and relocation of same car wash pad. 2. Reduction of 2 No. main ID signs to 1 No. main ID sign. 3. Removal of advertising bill board at the north end of the site. 4. Relocation of refuse storage area. 5. Alterations to boundary treatments
Development Address:
Rath Service Station , Rath, Ashbourne , Co. Meath
Architect Name:
J.A. Gorman
Location Key:
RATH
Electoral Division:
Incorrect Icl Voter Recor
Planner:
None
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Levies on this permission have been reduced by levies paid on permission DA/40222 as advised by Euge
Decision
Decision Date:
27/04/2006
Manager Order:
DN/182/06
Decision Type:
Conditional
Number of Conditions:
28
Grant Date:
27/06/2006
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
27/06/2011
Decision Description:
1. demolish existing service station/garage buildings and dwelling. 2. Construct new service station shop building containing 100 sq.m retail area with ancillary food bar area of 70 sq.m with associated storage and ancillary facilities. 3. Install 4 no fuel dispensing islands. 4. Install forecourt canopy over fuel dispensing pump islands. 5. Install 3 no. 40,000 L underground fuel tanks. 6. Install 2 no. car wash pads and service area. 7. Construct a fenced ancillary area to include refuse holding area. 8. Install 2 no. main ID signs. Further information submitted in realtion to planning application DA/50475 in which the following amendments have been made; 1. Reduction of 2. No. car wash pads to 1 No. car wash pad with splash screens and relocation of same car wash pad. 2. Reduction of 2 No. main ID signs to 1 No. main ID sign. 3. Removal of advertising bill board at the north end of the site. 4. Relocation of refuse storage area. 5. Alterations to boundary treatments
the development will consist of minor changes to the dwelling house as constructed to include reduction in width of the sunroom and minor changes to the windows and external door sizes together with changes to the domestic garage as constructed including the increased ridge height and alterations to the windows and external doors
development which will consist of 1, demolishing existing forecourt canopy & erection of new canopy: 2, installation of 2 no. 40,000L underground fuel tank: 3, reconfiguration of 2 no. pump islands: 4, construction of extension to existing workshop building for new store and canteen (12.3sq.m): 5, change of use of existing car workshop to retail area, allowing for overall retail area of 111.4sq.m: 6, installation of a new main identification sign: 7, alterations to shop building front elevation including shop signage