Planning application details ref: LB180620 Meath CoCo

100%100% Complete (warning)

Planning Application: LB180620 (Meath CoCo)
File Number: LB180620
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 08/06/2018 Decision Due Date: 02/08/2018
Validated Date: 08/06/2018 Invalidated Date:
Further Info Requested: Further Info Received:
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 31/07/2018
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By: 12/07/2018

Applicant Details

Applicant name: Shannon Homes Drogheda Ltd
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: the proposed development will consist of the demolition of the existing habitable house and construction of 1 no. 4 storey office building consisting of 2 no. blocks with a shared corner entrance/reception area and a screened plant area, solar panels and equipment at roof level, providing a total GFA of 11,205 sq.m. The proposed road infrastructure includes a link street approximately 720m in length, including 3 no. roundabout junctions, and it is also proposed to extend a 230m long spur of the link street to the east to facilitate a connection to the existing school on Mill Road (Gaelscoil an Bhradain Feasa). The road infrastructure also includes the realignment of a section of Colpe Road and the realignment of the southern section of Mill Road, and includes proposed cycle lanes/paths access road to the commercial development and associated car park, footpaths, grass verge, public lighting and the provision of a footpath and cyclepath/cycle lane on Colpe Road to tie-in with the existing shared footpath/cyclepath, to the south-west of the railway line. The associated site and infrastructural works include the demolition of the existing habitable house and associated structures, provision of foul water drainage, surface water drainage including surface water storage facilities above and below ground, watermains and utilities, 280 no. total car parking spaces, including 6 no. disabled parking spaces, 93 no. cycle parking spaces, landscaping consisting of new tree planting, hedges, berms and grass planting, public lighting, bin stores, boundary walls and fences, cyclepaths and footpaths, EBS substation and switchroom, gas skid, pump house, and all associated site and infrastructural works on an application site area of c. 8.07 hectares
Development Address: Colpe Road, Colpe West, Drogheda, Co. Meath
Architect Name: Brian Hughes Location Key: COLP WEST
Electoral Division: Incorrect Icl Voter Recor Planner: Billy Joe Padden
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 31/07/2018 Manager Order: L259/18
Decision Type: Conditional Number of Conditions: 25
Grant Date: 14/09/2018 Grant Managers Order #: L259/18
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 13/09/2028
Decision Description: the proposed development will consist of the demolition of the existing habitable house and construction of 1 no. 4 storey office building consisting of 2 no. blocks with a shared corner entrance/reception area and a screened plant area, solar panels and equipment at roof level, providing a total GFA of 11,205 sq.m. The proposed road infrastructure includes a link street approximately 720m in length, including 3 no. roundabout junctions, and it is also proposed to extend a 230m long spur of the link street to the east to facilitate a connection to the existing school on Mill Road (Gaelscoil an Bhradain Feasa). The road infrastructure also includes the realignment of a section of Colpe Road and the realignment of the southern section of Mill Road, and includes proposed cycle lanes/paths access road to the commercial development and associated car park, footpaths, grass verge, public lighting and the provision of a footpath and cyclepath/cycle lane on Colpe Road to tie-in with the existing shared footpath/cyclepath, to the south-west of the railway line. The associated site and infrastructural works include the demolition of the existing habitable house and associated structures, provision of foul water drainage, surface water drainage including surface water storage facilities above and below ground, watermains and utilities, 280 no. total car parking spaces, including 6 no. disabled parking spaces, 93 no. cycle parking spaces, landscaping consisting of new tree planting, hedges, berms and grass planting, public lighting, bin stores, boundary walls and fences, cyclepaths and footpaths, EBS substation and switchroom, gas skid, pump house, and all associated site and infrastructural works on an application site area of c. 8.07 hectares

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: