Planning application details ref: RA170644 Meath CoCo

100%100% Complete (warning)

Planning Application: RA170644 (Meath CoCo)
File Number: RA170644
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 09/06/2017 Decision Due Date: 31/01/2018
Validated Date: 09/06/2017 Invalidated Date:
Further Info Requested: 02/08/2017 Further Info Received: 15/12/2017
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 30/01/2018
Leave to Appeal: Appeal Date: 23/02/2018
Commenced Date: Submissions By: 17/01/2018

Applicant Details

Applicant name: JBM Solar Developments Ltd
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: a 10 year permission for the construction of a Solar PV Energy Development comprising Solar Photovoltaic (PV) panels on ground mounted frames/support structures within existing field boundaries; underground cabling and ducting; 24 no. inverter/transformer stations; 24 no. HV Cabins; 2 no. electricity control buildings; 1 no. communications cabin; site perimeter (stock proof) security fencing (c.85.3ha); CCTV security cameras; site access tracks; landscaping; and all associated site development works. Two temporary construction compounds will also be provided, one to each side of the site. Significant further information/revised plans submitted on this application
Development Address: Fidorfe, Grange and part of, Ratoath Manor, Co. Meath
Architect Name: Justin Farrelly Location Key: FIDORFE
Electoral Division: Incorrect Icl Voter Recor Planner: Kathryn Hosey
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 30/01/2018 Manager Order: R124/18
Decision Type: Conditional Number of Conditions: 13
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 11/12/2028
Decision Description: a 10 year permission for the construction of a Solar PV Energy Development comprising Solar Photovoltaic (PV) panels on ground mounted frames/support structures within existing field boundaries; underground cabling and ducting; 24 no. inverter/transformer stations; 24 no. HV Cabins; 2 no. electricity control buildings; 1 no. communications cabin; site perimeter (stock proof) security fencing (c.85.3ha); CCTV security cameras; site access tracks; landscaping; and all associated site development works. Two temporary construction compounds will also be provided, one to each side of the site. Significant further information/revised plans submitted on this application

Appeal Details


Appeal Details
Notification Date: 28/02/2018 BP Reference #: ABP-301023-18
Appeal Type: THIRD PARTY File Forward Date: 09/03/2018
Submission Due Date: 27/03/2018 Submission Sent Date: 27/03/2018
Appeal Decision: CONDITIONAL Decision Date: 12/12/2018
Withdrawn Date: Dismissed Date:
Reason: