Planning Application: 071650 (Roscommon County Council )
File Number:
071650
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
07/09/2007
Decision Due Date:
01/11/2007
Validated Date:
07/09/2007
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
31/10/2007
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
ESB Telecoms,
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
For the erection of a 36 metre high, free standing lattice communicaions structure, carrying antennae and communication dishes, with associated ground-mounted equipment cabinets, to be shared with third party operators, within a 2.4m high palisade compound, at ESB's existing Flagford 220kV substation, at
For the erection of a 36 metre high, free standing lattice communicaions structure, carrying antennae and communication dishes, with associated ground-mounted equipment cabinets, to be shared with third party operators, within a 2.4m high palisade compound, at ESB's existing Flagford 220kV substation, at
Erect a 110kV line bay in existing Flagford 220kV station to include the following current transformer, voltage transformer, circuit breaker, disconnects & ass. steelwork (excl. existing steel portals) at
for the Flagford 220kV Station Reinforcement project involving: (1) Install a 220kV transformer bay comprising of busbar disconnects, circuit breaker, current transformers (CT), voltage transformers (VT) and surge arresters. (2) Install a 125MVA 220kV/110kV auto-transformer. (3) Install a 110kV transformer bay comprised of surge arresters, combined CT/VT'S, a circuit breaker and busbar disconnects. Works will be carried out within the boundary fence of Flagford 220kV Station located at
No Environment Impact Assesments Associated with this Application