PP - development consisting of a renewable energy development on a 3.9 hectare site. The proposed development will constitute the provision of the following: Construction of a Biomass processing and storage area utilising forestry products. Construction of a Gasification and Methanation Plant including buildings for the production of advanced biofuels. Construction of a Gasification and Combined Heat Power Plant including building for the production of electricity and heating. Construction of Containerised Battery Storage Facility (20MW). Construction of a Thermal Energy recovery and storage facility including buildings for district heating distribution. Construction of two on-site 38kV substations. Creation of a new access from Finisklin Road. All ancillary development , including the provision of site office, car parking, internal access roads, perimeter landscaping, fencing, lighting, and on-site drainage. The Planning application is accompanied by a Natura Impact Statement.
Development Address:
Finisklin, Finisklin Road, Co Sligo
Architect Name:
Mark Forbes
Location Key:
FINISKLIN
Electoral Division:
Planner:
06
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
20/10/2021
Manager Order:
P538/21
Decision Type:
Refused
Number of Conditions:
3
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
Decision Description:
PP - development consisting of a renewable energy development on a 3.9 hectare site. The proposed development will constitute the provision of the following: Construction of a Biomass processing and storage area utilising forestry products. Construction of a Gasification and Methanation Plant including buildings for the production of advanced biofuels. Construction of a Gasification and Combined Heat Power Plant including building for the production of electricity and heating. Construction of Containerised Battery Storage Facility (20MW). Construction of a Thermal Energy recovery storage facility including buildings for district heating distribution. Construction of two on-site 38kV substations. Creation of a new access from Finisklin Road. All ancillary development , including the provision of site office, car parking, internal access roads, perimeter landscaping, fencing, lighting, and on-site drainage. The Planning application is accompanied by a Natura Impact Statement.