Planning application details ref: 21334 Sligo CoCo

100%100% Complete (warning)

Planning Application: 21334 (Sligo CoCo)
File Number: 21334
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 27/08/2021 Decision Due Date: 21/10/2021
Validated Date: 27/08/2021 Invalidated Date:
Further Info Requested: Further Info Received:
Withdrawn Date: Extend Date:
Decision Type: Refused Decision Date: 20/10/2021
Leave to Appeal: Appeal Date: 19/11/2021
Commenced Date: Submissions By: 30/09/2021

Applicant Details

Applicant name: Carbon Sole Group Limited
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: PP - development consisting of a renewable energy development on a 3.9 hectare site. The proposed development will constitute the provision of the following: Construction of a Biomass processing and storage area utilising forestry products. Construction of a Gasification and Methanation Plant including buildings for the production of advanced biofuels. Construction of a Gasification and Combined Heat Power Plant including building for the production of electricity and heating. Construction of Containerised Battery Storage Facility (20MW). Construction of a Thermal Energy recovery and storage facility including buildings for district heating distribution. Construction of two on-site 38kV substations. Creation of a new access from Finisklin Road. All ancillary development , including the provision of site office, car parking, internal access roads, perimeter landscaping, fencing, lighting, and on-site drainage. The Planning application is accompanied by a Natura Impact Statement.
Development Address: Finisklin, Finisklin Road, Co Sligo
Architect Name: Mark Forbes Location Key: FINISKLIN
Electoral Division: Planner: 06
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 20/10/2021 Manager Order: P538/21
Decision Type: Refused Number of Conditions: 3
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date:
Decision Description: PP - development consisting of a renewable energy development on a 3.9 hectare site. The proposed development will constitute the provision of the following: Construction of a Biomass processing and storage area utilising forestry products. Construction of a Gasification and Methanation Plant including buildings for the production of advanced biofuels. Construction of a Gasification and Combined Heat Power Plant including building for the production of electricity and heating. Construction of Containerised Battery Storage Facility (20MW). Construction of a Thermal Energy recovery storage facility including buildings for district heating distribution. Construction of two on-site 38kV substations. Creation of a new access from Finisklin Road. All ancillary development , including the provision of site office, car parking, internal access roads, perimeter landscaping, fencing, lighting, and on-site drainage. The Planning application is accompanied by a Natura Impact Statement.

Appeal Details


Appeal Details
Notification Date: 19/11/2021 BP Reference #: ABP-311963-21
Appeal Type: THIRD PARTY File Forward Date: 03/12/2021
Submission Due Date: 16/12/2021 Submission Sent Date: 15/12/2021
Appeal Decision: REFUSED Decision Date: 30/01/2023
Withdrawn Date: Dismissed Date:
Reason: