Planning application details ref: 16600565 Tipperary County Council

100%100% Complete (warning)

Planning Application: 16600565 (Tipperary County Council )
File Number: 16600565
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 20/06/2016 Decision Due Date: 25/10/2016
Validated Date: 20/06/2016 Invalidated Date:
Further Info Requested: 12/08/2016 Further Info Received: 28/09/2016
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 21/10/2016
Leave to Appeal: Appeal Date: 15/11/2016
Commenced Date: Submissions By:

Applicant Details

Applicant name: Lightsource Renewable Energy Ireland Limited
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: a ten year permission for the construction, operation and decommissioning of a solar photovoltaic panel array to export electricity to the national grid. The proposed works will include a 19.10 MWp solar farm comprising photovoltaic panels on ground mounted frames, 10 no. inverter stations, 1 no. single storey substation, 5 no. field transformer, 1 no. single storey communications building, 1 no. single storey storage shed, 1 no. battery container, 1 no. transformer container, 1 no. WC, fencing, temporary construction compound, access track, CCTV and all associated ancillary development works
Development Address: Monaraha, Cahir, Co. Tipperary
Architect Name: Location Key: MONARAHA
Electoral Division: Planner: JF
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 21/10/2016 Manager Order:
Decision Type: Conditional Number of Conditions: 17
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date:
Decision Description: a ten year permission for the construction, operation and decommissioning of a solar photovoltaic panel array to export electricity to the national grid. The proposed works will include a 19.10 MWp solar farm comprising photovoltaic panels on ground mounted frames, 10 no. inverter stations, 1 no. single storey substation, 5 no. field transformer, 1 no. single storey communications building, 1 no. single storey storage shed, 1 no. battery container, 1 no. transformer container, 1 no. WC, fencing, temporary construction compound, access track, CCTV and all associated ancillary development works

Appeal Details


Appeal Details
Notification Date: 17/11/2016 BP Reference #: 92.247589
Appeal Type: APPLICANT File Forward Date:
Submission Due Date: 14/12/2016 Submission Sent Date:
Appeal Decision: CONDITIONAL Decision Date: 06/02/2017
Withdrawn Date: Dismissed Date:
Reason: