Planning application details ref: 2260121 Tipperary County Council

100%100% Complete (warning)

Planning Application: 2260121 (Tipperary County Council )
File Number: 2260121
Application Type: PERMISSION Planning Status: APPEALED FINANCIAL
Received Date: 14/03/2022 Decision Due Date: 20/09/2022
Validated Date: 14/03/2022 Invalidated Date:
Further Info Requested: 05/05/2022 Further Info Received: 27/07/2022
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 20/09/2022
Leave to Appeal: Appeal Date: 12/10/2022
Commenced Date: Submissions By: 30/08/2022

Applicant Details

Applicant name: Miltown Composting Systems Ltd
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: reconstruction and extension of existing agricultural storage structure including use as organic material maturation and extension to existing storage facility, increase in allowed intake of organic material from 50,000 to 75,000 tonnes per annum to the processing facility, air handling bio-filter installation and associated extract and input fans, all necessary site works, an Environmental Impact Assessment (EIAR) will be submitted with the application to Tipperary Co. Co. with the planning application and the proposed development will require a review of the site’s EPA Industrial Emissions Licence (W0270-02)
Development Address: Milltownmore,, Fethard, Co. Tipperary, E91X8E8
Architect Name: Alan Walsh Walsh & Walsh Architects Location Key: MILTOWNMORE
Electoral Division: Planner: Lauren Butler Ryan
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: Yes Waste Licence Required: Yes
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 20/09/2022 Manager Order:
Decision Type: Conditional Number of Conditions: 8
Grant Date: 05/12/2023 Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 04/12/2028
Decision Description: reconstruction and extension of existing agricultural storage structure including use as organic material maturation and extension to existing storage facility, increase in allowed intake of organic material from 50,000 to 75,000 tonnes per annum to the processing facility, air handling bio-filter installation and associated extract and input fans, all necessary site works, an Environmental Impact Assessment (EIAR) will be submitted with the application to Tipperary Co. Co. with the planning application and the proposed development will require a review of the site’s EPA Industrial Emissions Licence (W0270-02)

Appeal Details


Appeal Details
Notification Date: 17/10/2022 BP Reference #: ABP-314834-22
Appeal Type: APPLICANT File Forward Date: 20/10/2022
Submission Due Date: 13/11/2022 Submission Sent Date: 09/11/2022
Appeal Decision: MODIFIED Decision Date: 05/12/2023
Withdrawn Date: Dismissed Date:
Reason: