Planning application details ref: 2360763 Tipperary County Council

100%100% Complete (warning)

Planning Application: 2360763 (Tipperary County Council )
File Number: 2360763
Application Type: PERMISSION Planning Status: APPEALED
Received Date: 22/09/2023 Decision Due Date: 16/11/2023
Validated Date: 22/09/2023 Invalidated Date:
Further Info Requested: Further Info Received:
Withdrawn Date: Extend Date:
Decision Type: Refused Decision Date: 16/11/2023
Leave to Appeal: Appeal Date: 13/12/2023
Commenced Date: Submissions By: 26/10/2023

Applicant Details

Applicant name: Carrig Renewable Energy Limited
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: (1) The construction of 7 no. wind turbines and associated hardstand areas with the following parameters a) total tip height range of 179.5m – 185m, b) rotor diameter range of 149m – 163m, c) hub height range of 103.5m to 110.5m; (2) 1 no. permanent 38kV electrical substation which will be constructed in the townland of Faddan Beg consisting of a single storey control building with welfare facilities, all associated electrical plant and equipment, battery energy storage system, security fencing, all associated underground cabling, wastewater holding tank and all ancillary works and equipment; (3) All works (within County Tipperary) associated with the connection of the proposed wind farm to the national electricity grid, via the provision of underground electrical cabling (38kV) to the existing Dallow 110kV substation in the townland of Clondallow, Co. Offaly; (4) Provision of 10 no. joint bays, communication chambers and earth sheath links along the underground electrical cabling route; (5) reinstatement of the road or track surface above the proposed cabling trench along existing roads and tracks; (6) all associated underground electrical and communications cabling connecting the turbines to the proposed wind farm substation; (7) 1 no. meteorological mast with a height of 107m above ground and associated foundation and hard-standing area; (8) upgrade of existing tracks and roads and the provision of new site access roads; (9) all works associated with the provision of a new permanent site entrance off the L5040 local road; (10) provision of 5 no. new access and egress points along the L5041 local road in the townlands of Cloncorig, Faddan More and Coolderry; (11) Provision of 4 no. peat repository areas and 3 no. spoil repository areas; (12) 2 no. temporary construction compounds with temporary site offices and staff facilities; (13) Accommodation works along the public road network along the N52 national secondary road in the townland of Ballyloughnane to facilitate the delivery of turbine components and other abnormal sized loads; (14) Site Drainage; (15) Tree Felling; (16) Operational stage site signage; and, (17) all associated site development works, ancillary works and apparatus. - Works within the curtilage of Protected Structures RPS Ref. TRPS336 (Ballyloughnane Bridge) and RPS Ref. TRPS519 (Croghan Bridge)
Development Address: In the townlands of Croghan, Clohaskin, Caherhoereigh, Ballykinash, Tinnakilly, Arragh More, Ballyloughnane, Faddan Beg, Coolderry,, Tinlough, Sharragh, Doughkill, Ballaghgar, Faddan More,, Cloncorig, Killeen, and Cornhill, Co. Tipperary
Architect Name: Location Key: Multiple locations
Electoral Division: Planner: MARION CAREY
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: Yes Protected Structure #: TRPS336 and TRPS519
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 16/11/2023 Manager Order:
Decision Type: Refused Number of Conditions: 3
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date:
Decision Description: (1) The construction of 7 no. wind turbines and associated hardstand areas with the following parameters a) total tip height range of 179.5m – 185m, b) rotor diameter range of 149m – 163m, c) hub height range of 103.5m to 110.5m; (2) 1 no. permanent 38kV electrical substation which will be constructed in the townland of Faddan Beg consisting of a single storey control building with welfare facilities, all associated electrical plant and equipment, battery energy storage system, security fencing, all associated underground cabling, wastewater holding tank and all ancillary works and equipment; (3) All works (within County Tipperary) associated with the connection of the proposed wind farm to the national electricity grid, via the provision of underground electrical cabling (38kV) to the existing Dallow 110kV substation in the townland of Clondallow, Co. Offaly; (4) Provision of 10 no. joint bays, communication chambers and earth sheath links along the underground electrical cabling route; (5) reinstatement of the road or track surface above the proposed cabling trench along existing roads and tracks; (6) all associated underground electrical and communications cabling connecting the turbines to the proposed wind farm substation; (7) 1 no. meteorological mast with a height of 107m above ground and associated foundation and hard-standing area; (8) upgrade of existing tracks and roads and the provision of new site access roads; (9) all works associated with the provision of a new permanent site entrance off the L5040 local road; (10) provision of 5 no. new access and egress points along the L5041 local road in the townlands of Cloncorig, Faddan More and Coolderry; (11) Provision of 4 no. peat repository areas and 3 no. spoil repository areas; (12) 2 no. temporary construction compounds with temporary site offices and staff facilities; (13) Accommodation works along the public road network along the N52 national secondary road in the townland of Ballyloughnane to facilitate the delivery of turbine components and other abnormal sized loads; (14) Site Drainage; (15) Tree Felling; (16) Operational stage site signage; and, (17) all associated site development works, ancillary works and apparatus. - Works within the curtilage of Protected Structures RPS Ref. TRPS336 (Ballyloughnane Bridge) and RPS Ref. TRPS519 (Croghan Bridge)

Appeal Details


Appeal Details
Notification Date: 14/12/2023 BP Reference #: ABP-318689-23
Appeal Type: APPLICANT File Forward Date: 20/12/2023
Submission Due Date: 12/01/2024 Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: