Planning application details ref: 161380 Wicklow County Council

100%100% Complete (warning)

Planning Application: 161380 (Wicklow County Council )
File Number: 161380
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 13/12/2016 Decision Due Date: 12/04/2017
Validated Date: 13/12/2016 Invalidated Date:
Further Info Requested: 14/02/2017 Further Info Received: 16/03/2017
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 05/04/2017
Leave to Appeal: Appeal Date: 02/05/2017
Commenced Date: Submissions By:

Applicant Details

Applicant name: Gaelectric Renewable Energy Developments Ltd
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: ten year permission for the development of a solar photovoltaic (PV) energy development to include a single storey electrical substation building, electrical inverter and transformer stations, solar PV panels mounted on metal frames, upgraded and new access tracks, underground cabling, perimeter fencing with infrared CCTV and access gates, temporary construction compound spare parts container, weather station, an upgraded access point and all ancillary infrastructure and associated works within a total site area of up to 57 acres
Development Address: Ballinaclogh, Rathnew, Co. Wicklow
Architect Name: Location Key: BALLINCLOGH
Electoral Division: Planner: Lyndsey Blackmore
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments: Ten Year Permission

Decision

Decision Date: 05/04/2017 Manager Order: 327/17
Decision Type: Conditional Number of Conditions: 14
Downloads a Microsoft Word Document (Document Size 20 Kb)

Download a Free Word viewer
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 08/02/2023
Decision Description: ten year permission for the development of a solar photovoltaic (PV) energy development to include a single storey electrical substation building, electrical inverter and transformer stations, solar PV panels mounted on metal frames, upgraded and new access tracks, underground cabling, perimeter fencing with infrared CCTV and access gates, temporary construction compound, spare parts container, weather station, an upgraded access point and all ancillary infrastructure and associated works within a total site area of up to 57 acres

Appeal Details


Appeal Details
Notification Date: 03/05/2017 BP Reference #: PL 27.248424
Appeal Type: THIRD PARTY File Forward Date: 10/05/2017
Submission Due Date: 30/05/2017 Submission Sent Date:
Appeal Decision: CONDITIONAL Decision Date: 09/02/2018
Withdrawn Date: Dismissed Date:
Reason: 17