Planning Application: 18940 (Wicklow County Council )
File Number:
18940
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
20/08/2018
Decision Due Date:
20/02/2019
Validated Date:
20/08/2018
Invalidated Date:
Further Info Requested:
11/10/2018
Further Info Received:
18/12/2018
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
15/02/2019
Leave to Appeal:
Appeal Date:
14/03/2019
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Crag Digital Avoca Ltd
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
demolition of buildings & structures on site & construction of Data Storage Facility comprising 3 data storage buildings & all assoc site infrastructure: data storage facility 1 (6 Pod Data Centre) located to north of site served by 1 gas generator compound to south of Data Storage building including 5 flues & 2 bunded fuel tanks located to south east & south west of Data Storage building & powered by (-part grid / - part gas) with emergency diesel fuel backup. Data storage facility 2 (8 pod data centre) located to south of Data Storage Facility 1 served by 1 gas generator compound to the south of building incl 6 flues & 2 bunded fuel tanks located to south east & south west of Data Storage building & powered by (-part grid / -part gas) with emergency diesel fuel backup. Data storage 3 (8 pod data centre) located to south of site served by 1 diesel generator compound to north of building incl 8 flues & 2 bunded fuel tanks, located to north east & north west of Data Storage building & powered by grid. The dev will consist of upgrade of existing 100 kV substation to provide a Substation Compound comprising Gas Insulated Switchgear (GIS) equipment with 4 50 mega Volt Amp bays within a single storey MV building 10 lighting protection masts, 4 oil filled transformers, with c2.4m high palisade fence, provision of 1 single storey security guard house at primary access to data storage facilities, provision of 4 vehicular access points off Shelton Abbey (access rd) on western side (2 to serve Data Storage Facilities, 1 to serve GIS substation & 1 to serve MV building), internal access roads, surface level car parking, site services (foul & surface water drainage & water supply) incl 1 pump house with 3 water tanks to sough west, 1 attenuation pond to south east, waste water treatment plant to the west of Shelton Abbey (access road), landscaping, boundary & site dev works above & below ground. Accompany by EIAR
Development Address:
Avoca River Park, Shelton Abbey & Kilbride, Arklow, Co. Wicklow
Architect Name:
Location Key:
SHELTON ABBEY
Electoral Division:
Planner:
None
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
ABP received a 3rd party appeal on 14/03/19
Decision
Decision Date:
15/02/2019
Manager Order:
254/19
Decision Type:
Conditional
Number of Conditions:
25
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
16/07/2024
Decision Description:
demolition of buildings & structures on site & construction of Data Storage Facility comprising 3 data storage buildings & all assoc site infrastructure: data storage facility 1 (6 Pod Data Centre) located to north of site served by 1 gas generator compound to south of Data Storage building including 5 flues & 2 bunded fuel tanks located to south east & south west of Data Storage building & powered by (-part grid / - part gas) with emergency diesel fuel backup. Data storage facility 2 (8 pod data centre) located to south of Data Storage Facility 1 served by 1 gas generator compound to the south of building incl 6 flues & 2 bunded fuel tanks located to south east & south west of Data Storage building & powered by (-part grid / -part gas) with emergency diesel fuel backup. Data storage 3 (8 pod data centre) located to south of site served by 1 diesel generator compound to north of building incl 8 flues & 2 bunded fuel tanks, located to north east & north west of Data Storage building & powered by grid. The dev will consist of upgrade of existing 100 kV substation to provide a Substation Compound comprising Gas Insulated Switchgear (GIS) equipment with 4 50 mega Volt Amp bays within a single storey MV building 10 lighting protection masts, 4 oil filled transformers, with c2.4m high palisade fence, provision of 1 single storey security guard house at primary access to data storage facilities, provision of 4 vehicular access points off Shelton Abbey (access rd) on western side (2 to serve Data Storage Facilities, 1 to serve GIS substation & 1 to serve MV building), internal access roads, surface level car parking, site services (foul & surface water drainage & water supply) incl 1 pump house with 3 water tanks to sough west, 1 attenuation pond to south east, waste water treatment plant to the west of Shelton Abbey (access road), landscaping, boundary & site dev works above & below ground. Accompany by EIAR
demolition of buildings & structures on site & construction of Data Storage Facility comprising 3 data storage buildings & all assoc site infrastructure: data storage facility 1 (6 Pod Data Centre) located to north of site served by 1 gas generator compound to south of Data Storage building including 5 flues & 2 bunded fuel tanks located to south east & south west of Data Storage building & powered by (-part grid / - part gas) with emergency diesel fuel backup. Data storage facility 2 (8 pod data centre) located to south of Data Storage Facility 1 served by 1 gas generator compound to the south of building incl 6 flues & 2 bunded fuel tanks located to south east & south west of Data Storage building & powered by (-part grid / -part gas) with emergency diesel fuel backup. Data storage 3 (8 pod data centre) located to south of site served by 1 diesel generator compound to north of building incl 8 flues & 2 bunded fuel tanks, located to north east & north west of Data Storage building & powered by grid. The dev will consist of upgrade of existing 100 kV substation to provide a Substation Compound comprising Gas Insulated Switchgear (GIS) equipment with 4 50 mega Volt Amp bays within a single storey MV building 10 lighting protection masts, 4 oil filled transformers, with c2.4m high palisade fence, provision of 1 single storey security guard house at primary access to data storage facilities, provision of 4 vehicular access points off Shelton Abbey (access rd) on western side (2 to serve Data Storage Facilities, 1 to serve GIS substation & 1 to serve MV building), internal access roads, surface level car parking, site services (foul & surface water drainage & water supply) incl 1 pump house with 3 water tanks to sough west, 1 attenuation pond to south east, waste water treatment plant to the west of Shelton Abbey (access road), landscaping, boundary & site dev works above & below ground. Accompany by EIAR