Planning Application: 2113 (Carlow County Council )
File Number:
2113
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
22/01/2021
Decision Due Date:
18/03/2021
Validated Date:
22/01/2021
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Refused
Decision Date:
18/03/2021
Leave to Appeal:
Appeal Date:
13/04/2021
Commenced Date:
Submissions By:
25/02/2021
Applicant Details
Applicant name:
Coillte CGA
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
Permission to develop a wind farm and associated works . The proposed development will consist of: - Construction of up to 7 no. wind turbines with a maximum overall blade tip height of up to 178m; - Construction of turbine foundations and crane pad hardstanding areas; - Construction of new site tracks and associated drainage infrastructure; - Upgrading of existing tracts and associated drainage infrastructure where necessary including upgrade of entrance onto L2026; - All associated drainage and sediment control including the installation of new watercourse or drain crossings and the re-use or upgrading of existing internal watercourse and drain crossings; - Construction of 1 no. permanent onsite 38kV electrical substation to ESBN specifications including: Control building with welfare facilities; - Electrical infrastructure; - Parking; - Wastewater holding tank; - rainwater harvesting; - Security fencing; - All associated infrastructure, services and site works; - 1 no. temporary construction site compound and associated ancillary infrastructure including parking; - 1 no. on site borrow pit (the borrow pit shall be accessed via wind farm access tracks); - Tree felling to facilitate construction and operation of the proposed development; - Installation of medium voltage (20/33kV) and communication underground cabling between the proposed turbines and the proposed on-site substation and associated ancillary works; - Erection of 1 no. permanent meteorological mast to a maximum height of 100m above ground level; - Upgrade of existing forest tracks and paths that shall be re-purposed as recreational amenity trails for community use including signage; - All associated site development works; - A 10 year planning permission and 35 year operational life from the date of commissioning of the entire wind farm. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development and will be submitted with the application.
Permission to develop a wind farm and associated works . The proposed development will consist of: - Construction of up to 7 no. wind turbines with a maximum overall blade tip height of up to 178m; - Construction of turbine foundations and crane pad hardstanding areas; - Construction of new site tracks and associated drainage infrastructure; - Upgrading of existing tracts and associated drainage infrastructure where necessary including upgrade of entrance onto L2026; - All associated drainage and sediment control including the installation of new watercourse or drain crossings and the re-use or upgrading of existing internal watercourse and drain crossings; - Construction of 1 no. permanent onsite 38kV electrical substation to ESBN specifications including: Control building with welfare facilities; - Electrical infrastructure; - Parking; - Wastewater holding tank; - rainwater harvesting; - Security fencing; - All associated infrastructure, services and site works; - 1 no. temporary construction site compound and associated ancillary infrastructure including parking; - 1 no. on site borrow pit (the borrow pit shall be accessed via wind farm access tracks); - Tree felling to facilitate construction and operation of the proposed development; - Installation of medium voltage (20/33kV) and communication underground cabling between the proposed turbines and the proposed on-site substation and associated ancillary works; - Erection of 1 no. permanent meteorological mast to a maximum height of 100m above ground level; - Upgrade of existing forest tracks and paths that shall be re-purposed as recreational amenity trails for community use including signage; - All associated site development works; - A 10 year planning permission and 35 year operational life from the date of commissioning of the entire wind farm. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development and will be submitted with the application.