Planning application details ref: 22163 Carlow County Council

100%100% Complete (warning)

Planning Application: 22163 (Carlow County Council )
File Number: 22163
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 20/05/2022 Decision Due Date: 16/02/2023
Validated Date: 20/05/2022 Invalidated Date:
Further Info Requested: 13/07/2022 Further Info Received: 20/01/2023
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 16/02/2023
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By:

Applicant Details

Applicant name: Garreenleen Solar Farm Limited
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: for a 10 year planning permission for a solar farm and associated works, comprising (1) A solar farm which will connect to the national electricity grid on lands with a total area of circa 128 hectares, consisting of solar panels on ground mounted frames, 18 no. single storey electrical inverter/transformer stations, equipment container, underground cabling within the solar farm site and within the N80 and L-3046 public roads to connect solar farm field parcels, security fencing, satellite communications pole, CCTV, access tracks inclusive of 9 no. agricultural bridges (including 1 no. bridge over the river Burrin), temporary construction compounds, landscaping and all associated ancillary development works. (2) minor amendments to a neighbouring solar farm planning permission (Carlow County Council planning reference 20143 & An Bord Pleanala reference: 307891-20) to facilitate future grid connection and additional access tracks for the proposed development. These amendments will comprise of the removal of 1,837 sqm of solar panels, provision of additional access tracks and focused removal of hedgerows to accommodate same, and the laying of 1,788 metres of 33kV underground cabling for the purposes of the future grid connection. (3) Construction and operational access for the solar farm will be via entrances from the L-7111, L-3046 and L-3049. The operational lifespan of the solar farm will be 35 years. A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning authority with the application.
Development Address: Ballintrane Ballybrommell, Bendinstown, Clonmacshane, Garreenleen, Graiguealug, Tinnaclash & Templepeter, Co. Carlow
Architect Name: Location Key: GARREENLEEN
Electoral Division: Planner: Wesley Keogh
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 16/02/2023 Manager Order: 34687
Decision Type: Conditional Number of Conditions: 28
Downloads a Microsoft Word Document (Document Size 35 Kb)

Download a Free Word viewer
Grant Date: 22/03/2023 Grant Managers Order #: 34687
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 21/03/2033
Decision Description: for a 10 year planning permission for a solar farm and associated works, comprising (1) A solar farm which will connect to the national electricity grid on lands with a total area of circa 128 hectares, consisting of solar panels on ground mounted frames, 18 no. single storey electrical inverter/transformer stations, equipment container, underground cabling within the solar farm site and within the N80 and L-3046 public roads to connect solar farm field parcels, security fencing, satellite communications pole, CCTV, access tracks inclusive of 9 no. agricultural bridges (including 1 no. bridge over the river Burrin), temporary construction compounds, landscaping and all associated ancillary development works. (2) minor amendments to a neighbouring solar farm planning permission (Carlow County Council planning reference 20143 & An Bord Pleanala reference: 307891-20) to facilitate future grid connection and additional access tracks for the proposed development. These amendments will comprise of the removal of 1,837 sqm of solar panels, provision of additional access tracks and focused removal of hedgerows to accommodate same, and the laying of 1,788 metres of 33kV underground cabling for the purposes of the future grid connection. (3) Construction and operational access for the solar farm will be via entrances from the L-7111, L-3046 and L-3049. The operational lifespan of the solar farm will be 35 years. A Natura Impact Statement (NIS) has been prepared and will be submitted to the planning authority with the application.

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: