DEVELOPMENT OF A 7.2 MW WINDFARM COMPRISING OF 8 NO. 900KW WIND TURBINES, WITH STEEL TOWERS AND COMPOSITE FIBRE ROTOR BLADES, OF HUB HEIGHT UP TO A MAXIMUM 55 METRES, A ROTOR DIAMETER OF UP TO MAXIMUM 44 METRES AND BASE TO BLADE TIP HEIGHT OF UP TO A MAXIMUM 77 METRES. THE DEVELOPMENT WILL ALSO INCLUDE WIND TURBINE TRANSFORMERS, A TURBINE HARDSTAND, NEW ACCESS ROADS 4.5 METRES IN WIDTH, STRENGTHENING AND WIDENING OF EXISTING ACCESS ROADS, DRAINAGE, A SUBSTATION CONTROL BUILDING WITH FENCED COMPOUND FOR ELECTRICAL EQUIPMENT, A 54 METRE HIGH METEOROLOGICAL MEASURING MAST, TEMPORARY QUARRY, UNDERGROUND COMMUNICATION AND POWER CABLES AND ALL ASSSOCIATED SITE WORKS AND ANCILLARY DEVELOPMENT
DEVELOPMENT OF A 7.2 MW WINDFARM COMPRISING OF 8 NO. 900KW WIND TURBINES, WITH STEEL TOWERS AND COMPOSITE FIBRE ROTOR BLADES, OF HUB HEIGHT UP TO A MAXIMUM 55 METRES, A ROTOR DIAMETER OF UP TO MAXIMUM 44 METRES AND BASE TO BLADE TIP HEIGHT OF UP TO A MAXIMUM 77 METRES. THE DEVELOPMENT WILL ALSO INCLUDE WIND TURBINE TRANSFORMERS, A TURBINE HARDSTAND, NEW ACCESS ROADS 4.5 METRES IN WIDTH, STRENGTHENING AND WIDENING OF EXISTING ACCESS ROADS, DRAINAGE, A SUBSTATION CONTROL BUILDING WITH FENCED COMPOUND FOR ELECTRICAL EQUIPMENT, A 54 METRE HIGH METEOROLOGICAL MEASURING MAST, TEMPORARY QUARRY, UNDERGROUND COMMUNICATION AND POWER CABLES AND ALL ASSSOCIATED SITE WORKS AND ANCILLARY DEVELOPMENT
CONSTRUCTION OF A 20KV OVERHEAD & UNDERGROUND ELECTRICITY CABLE TO SERVE APPROVED WINDFARM DEVELOPMENT. THE PLANNING APPLICATION IS ACCOMPANIED BY A NATURA IMPACT STATEMENT (NIS)
CONSTRUCTION OF AN ACCESS TRACK & ASSOCIATED SITE WORKS INCLUDING DRAINAGE AND UNDERGROUND ELECTRICAL CABLES TO SERVE PERMITTED SINGLE WIND TURBINE (PLANNING REFERENCE 16/50297 & 11/40003 REFER)
No Environment Impact Assesments Associated with this Application