Planning Application: 1851418 (Donegal County Council )
File Number:
1851418
Application Type:
PERMISSION
Planning Status:
WITHDRAWN
Received Date:
14/09/2018
Decision Due Date:
Validated Date:
14/09/2018
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
26/10/2018
Extend Date:
Decision Type:
Decision Date:
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
18/10/2018
Applicant Details
Applicant name:
MOONEY BOATS LIMITED
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
(1) DEMOLITION OF EXISTING SHED (MACHINE SHOP), (2) CONSTRUCTION OF A NEW BUILDING, STORAGE AREA ASSOCIATED WITH EXISTING RETAIL OUTLET (3) NEW MACHINE SHOP ASSOCIATED WITH EXISTING BOAT YARD AND (4) CONNECTION TO EXISTING ON-SITE SERVICES WITH ALL ASSOCIATED SITE DEVELOPMENTS WORKS
CONSTRUCTION OF NEW TWO STOREY RETAIL UNIT INCLUDING, OFFICES, TOILETS STORES, COFFEE DOCK AND SHOP DISPLAY AREA, EXTERNAL DISPLAY COMPOUND TO FRONT, GAS STORAGE YARD AND GENERAL YARD AREA TO REAR, CAR PARKING, PEDESTRIAN ACCESS FROM PUBLIC FOOTPATH, CONNECTION TO EXISTING PUBLIC SEWER AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
SHORE RD GLEBE TD KILLYBEGS FISHERY HARBOUR CENTRE
RETENTION OF DEVELOPMENT COVERING INFILLED TIDAL WATERS FOR EXTENSION OF OPEN YARD, OF APPROXIMATELY 0.10 HA AND CONSTRUCTION OF A NEW QUAY WALL/ BERTHING FACILITY WITHIN PROPERTY AND THE ADJACENT TIDAL WATERS OF KILLYBEGS HARBOUR, CONSISTING OF THE FOLLOWING WORKS: (1) INSTALLATION OF ROTARY CORE CONCRETE PILES APPROXIMATELY 7M DEEP TO FORM REQUIRED FOUNDATION TO STRUCTURE (20 INSTALLATION OF PRE CAST CONCRETE BEAMS FIXED TO PILES (3) CAST IN-SITU CONCRETE QUAY DECK, APPROXIMATELY 1079 SQ.M 0.3 ABOVE EXISTING YEAR (4) INSTALLATION OF UNDERGROUND SERVICE DUCTS AND ASSOCIATED SITE WORKS
SHORE RD. KILLYBEGS TD KILLYBEGS FISHERY HARBOUR CENTRE
RETENTION OF DEVELOPMENT COVERING IN-FILLED TIDAL WATERS FOR EXTENSION OF OPEN YARD, OF APPROXIMATELY 0.19 HA AND PERMISSION FOR DEVELOPMENT IS REQUESTED FOR THE CONSTRUCTION OF A NEW QUAY WALL/BERTHING FACILITY WITHIN THE PROPERTY AND THE ADJACENT TIDAL WATERS OF KILLYBEGS HARBOUR FOR THE BUILDING AND REPAIR OF TIDAL CRAFT CONSISTING OF THE FOLLOWING WORKS: INSTALLATION OF ROTARY CORE CONCRETE PILES APPROXIMATELY 7M DEEP TO FORM REQUIRED FOUNDATION TO STRUCTURE, INSTALLATION OF PRE CAST CONCRETE BEAMS FIXED TO PILES CAST IN-SITU CONCRETE QUAY DECK, APPROXIMATELY 515 SQ.M, 0.3M ABOVE EXISTING YARD LEVEL, INSTALLATION OF UNDERGROUND SERVICE DUCTS AND ASSOCIATED SITE WORKS
DEMOLITION OF EXISTING SHED (MACHINE SHOP), CONSTRUCTION OF A NEW BUILDING, STORAGE AREA ASSOCIATED WITH EXISTING RETAIL OUTLET AND NEW MACHINE SHOP ASSOCIATED WITH EXISTING BOAT YARD, CONNECTION TO EXISTING ON-SITE SERVICES WITH ALL ASSOCIATED SITE DEVELOPMENT WORKS
DEMOLITION OF A SECTION OF THE EXISTING SEA WALL IN COMBINATION WITH THE CONSTRUCTION OF A NEW ROCK ARMOUR REVETMENT AND A NEW BOUNDARY FENCE ON THE SOUTH-EAST OF THE EXISTING BOAT YARD FACILITY
ALTERATIONS AND CHANGE OF USE OF PART OF THE FRONT OF THE EXISTING SHOP TO PROVIDE A COFFEE DOCK FOR SALE OF FOOD AND BEVERAGES, WITH INTERNAL AND EXTERNAL SERVERY HATCHES AND PROVISION OF INTERNAL AND EXTERNAL SEATING TO INCLUDE PROVISION OF OPENINGS IN THE FRONT ELEVATION AND ELEVATION CHANGES
No Environment Impact Assesments Associated with this Application