Planning application details ref: 2350892 Donegal County Council

100%100% Complete (warning)

Planning Application: 2350892 (Donegal County Council )
File Number: 2350892
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 23/06/2023 Decision Due Date: 27/03/2024
Validated Date: 23/06/2023 Invalidated Date:
Further Info Requested: 10/08/2023 Further Info Received: 29/02/2024
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 21/03/2024
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By:

Applicant Details

Applicant name: DERRYKILLEW COMMUNITY WIND FARM LTD
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: (1) A 38KV UNDERGROUND CABLE GRID CONNECTION APPROXIMATELY 9KM IN LENGTH FROM THE CONSENTED DERRYKILLEW COMMUNITY WIND FARM (AN BORD PLEANÁLA REF. NO. 307520, DONEGAL COUNTY COUNCIL REF. NO. 19/51750) TO LANDS AT TOWNPARKS, NORTH OF THE EXISTING CATHALEEN'S FALL 110KV SUBSTATION IN BALLYSHANNON, (2) A PARTIAL SECTION OF A 38KV OVERHEAD LINE GRID CONNECTION CROSSING 130M OVER THE RIVER ERNE AT CATHALEEN'S FALL, BALLYSHANNON, AND (3) THE DERRYKILLEW COMMUNITY WIND FARM 38KV SUBSTATION AND A BATTERY ENERGY STORAGE SYSTEM. AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) ACCOMPANIES THIS APPLICATION
Development Address: DERRYKILLEW,, CORLEA, CASHELARD,, DOOBALLY, KNADER & TOWNPARKS, BALLYSHANNON, CO. DONEGAL
Architect Name: PADDY CURRAN Location Key: DERRYKILLEW
Electoral Division: Cliff Planner: Aideen Quinn
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 21/03/2024 Manager Order: 2024PH0625
Decision Type: Conditional Number of Conditions: 25
Grant Date: 24/04/2024 Grant Managers Order #: 2024PH0625
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 23/04/2029
Decision Description: (A) A 38KV UNDERGROUND CABLE GRID CONNECTION APPROXIMATELY 9KM IN LENGTH FROM THE CONSENTED DERRYKILLEW COMMUNITY WIND FARM (AN BORD PLEANÁLA REF: 307520, DONEGAL COUNTY COUNCIL REF: 1951750) TO LANDS AT TOWNPARKS, NORTH OF THE EXISTING CATHALEEN'S FALL 110KV SUBSTATION IN BALLYSHANNON, (B) A PARTIAL SECTION OF A 38KV OVERHEAD LINE GRID CONNECTION CROSSING 130M OVER THE RIVER ERNE AT CATHALEEN'S FALL, BALLYSHANNON, AND (C) THE DERRYKILLEW COMMUNITY WIND FARM 38KV SUBSTATION AND A BATTERY ENERGY STORAGE SYSTEM

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: