Planning application details ref: 99497 Donegal County Council

100%100% Complete (warning)

Planning Application: 99497 (Donegal County Council )
File Number: 99497
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 17/02/1999 Decision Due Date: 12/05/2000
Validated Date: 17/02/1999 Invalidated Date:
Further Info Requested: 08/04/1999 Further Info Received: 13/03/2000
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 04/05/2000
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By:

Applicant Details

Applicant name: ELECTRICITY SUPPLY BOARD
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: ERECTION OF NEW 110KV OVERHEAD LINES FROM EXISTING BINBANE 110KV SUBSTATION AT MEENACAHAN TO PROPOSED NEW DARRAGH 110KV SUBSTATION AT DORE TO EXISTING LETTERKENNY 110KV SUBSTATION AT LISTELLION
Development Address: MEENACAHAN- , DORE-LISTELLIAN
Architect Name: Location Key: LISTILLION
Electoral Division: Glenties Planner: None
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: Waste Licence Required:
Protected Structure: Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Yes Comments: E.I.S. SUBMITTED

Decision

Decision Date: 04/05/2000 Manager Order: 2000/P2585
Decision Type: Conditional Number of Conditions: 8
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date:
Decision Description: ERECTION OF NEW 110KV OVERHEAD LINES FROM EXISTING BINBANE 110KV SUBSTATION AT MEENACAHAN TO PROPOSED NEW DARRAGH 110KV SUBSTATION AT DORE TO EXISTING LETTERKENNY 110KV SUBSTATION AT LISTELLION

Appeal Details


Appeal Details
Notification Date: 13/06/2000 BP Reference #: 05119713
Appeal Type: THIRD PARTY File Forward Date: 19/06/2000
Submission Due Date: 12/07/2000 Submission Sent Date: 30/06/2000
Appeal Decision: REFUSED Decision Date: 29/06/2001
Withdrawn Date: Dismissed Date:
Reason: