Planning Application: 181883 (Galway County Council )
File Number:
181883
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
21/12/2018
Decision Due Date:
24/06/2019
Validated Date:
21/12/2018
Invalidated Date:
Further Info Requested:
21/02/2019
Further Info Received:
28/05/2019
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
21/06/2019
Leave to Appeal:
Appeal Date:
16/07/2019
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Engie Developments Ireland Limited
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
for a ten-year planning permission for the development of an up to 100MW Battery Energy Storage Facility that will provide energy services to the national grid and will be delivered in 4 no. phases. The development will consist of the construction and operation of up to 34 metal containers to store up to a project total of up to 100MW in sealed battery cells each with entrances, fire suppression systems, heating, ventilation and air conditioning systems. The proposed development includes for inverters, control systems, other electrical components, security lighting and ancillary infrastructure and all associated works including security fencing and ancillary grid infrastructure. Gross floor space of proposed works: 2186.6 sqm
Development Address:
Barrettspark
Architect Name:
Location Key:
BARRETTSPARK
Electoral Division:
Planner:
John O'Donnell
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
21/06/2019
Manager Order:
Decision Type:
Conditional
Number of Conditions:
6
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
11/11/2024
Decision Description:
for a ten-year planning permission for the development of an up to 100MW Battery Energy Storage Facility that will provide energy services to the national grid and will be delivered in 4 no. phases. The development will consist of the construction and operation of up to 34 metal containers to store up to a project total of up to 100MW in sealed battery cells each with entrances, fire suppression systems, heating, ventilation and air conditioning systems. The proposed development includes for inverters, control systems, other electrical components, security lighting and ancillary infrastructure and all associated works including security fencing and ancillary grid infrastructure. Gross floor space of proposed works: 2186.6 sqm