Planning application details ref: 19107 Galway City Council

100%100% Complete (warning)

Planning Application: 19107 (Galway City Council)
File Number: 19107
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 11/04/2019 Decision Due Date: 24/01/2020
Validated Date: 11/04/2019 Invalidated Date:
Further Info Requested: 04/06/2019 Further Info Received: 19/12/2019
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 24/01/2020
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By:

Applicant Details

Applicant name: Irish Water
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: Permission for development which comprises of a new raw water intake works located on the east bank of the River Corrib, 100m downstream of Quincentenary Bridge; associated pipework to transfer raw water from the new intake works to the existing intakes works , which in turn supplies Terryland Water Treatment Plant (WTP); and a new treated water rising main extending between Terryland WTP and existing rising main on the east bank of the River Corrib. The works comprises: New Intake Works. a) Underground inlet works chamber and associated equipment; b) Control building; c) Compound security fencing and gates, safety fencing, drainage, lighting, hard - standing areas and landscaping, ducting and water supply connection; d) Access road from Dyke Road with new entrance and gates; e) Floating boom system offset 5m inti the river from proposed headwall of the intake works. Slipway. f) A new slipway, including a new public access road from Dyke Road. The slipway will be located on the east bank of the River Corrib, circa. 140m downstream of the Quincentenary Bridge. Transfer Mains. g) 215m of 1200mm diameter underground transfer gravity main passing under Terryland parkland, the Quincentenary Bridge eastern approach road (N6) and Terryland River. This will connect the new intake works to the existing raw water mains, which supply Terryland WTP. Works will include 2 no. chambers along the transfer main ( north and south of the N6 Road) and 1 no. chamber for connection to the existing raw water mains at the existing intake site; h) Modifications to the existing intake works in Terryland (decommissioning and civil works). Rising Main. I) 535m of 600mm diameter ductile iron underground rising main from Terryland WTP of the eastern bank to the River Corrib, including a pipe - bridge over the Terryland River, to connect to the existing 450mm diameter ductile iron rising main upstream of the River Corrib crossing. Surge Vessel. j) 1 no. 35m3 surge vessel tank at Terryland WTP for the proposed rising main. A Natura Impact Statement has been submitted.
Development Address: Dyke Road, Terryland , Galway
Architect Name: Location Key: TERRYLAND
Electoral Division: Planner: Liam Blake
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 24/01/2020 Manager Order: 71530
Decision Type: Conditional Number of Conditions: 11
Grant Date: 24/02/2020 Grant Managers Order #: 71686
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 23/02/2025
Decision Description: Permission for development which comprises of a new raw water intake works located on the east bank of the River Corrib, 100m downstream of Quincentenary Bridge; associated pipework to transfer raw water from the new intake works to the existing intakes works , which in turn supplies Terryland Water Treatment Plant (WTP); and a new treated water rising main extending between Terryland WTP and existing rising main on the east bank of the River Corrib. The works comprises: New Intake Works. a) Underground inlet works chamber and associated equipment; b) Control building; c) Compound security fencing and gates, safety fencing, drainage, lighting, hard - standing areas and landscaping, ducting and water supply connection; d) Access road from Dyke Road with new entrance and gates; e) Floating boom system offset 5m inti the river from proposed headwall of the intake works. Slipway. f) A new slipway, including a new public access road from Dyke Road. The slipway will be located on the east bank of the River Corrib, circa. 140m downstream of the Quincentenary Bridge. Transfer Mains. g) 215m of 1200mm diameter underground transfer gravity main passing under Terryland parkland, the Quincentenary Bridge eastern approach road (N6) and Terryland River. This will connect the new intake works to the existing raw water mains, which supply Terryland WTP. Works will include 2 no. chambers along the transfer main ( north and south of the N6 Road) and 1 no. chamber for connection to the existing raw water mains at the existing intake site; h) Modifications to the existing intake works in Terryland (decommissioning and civil works). Rising Main. I) 535m of 600mm diameter ductile iron underground rising main from Terryland WTP of the eastern bank to the River Corrib, including a pipe - bridge over the Terryland River, to connect to the existing 450mm diameter ductile iron rising main upstream of the River Corrib crossing. Surge Vessel. j) 1 no. 35m3 surge vessel tank at Terryland WTP for the proposed rising main. A Natura Impact Statement has been submitted.

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: