Planning Application: 101302 (Kerry County Council )
File Number:
101302
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
21/12/2010
Decision Due Date:
23/02/2011
Validated Date:
21/12/2010
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Refused
Decision Date:
23/02/2011
Leave to Appeal:
Appeal Date:
22/03/2011
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
JOHN CREEDON
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
CONSTRUCT A SINGLE TURBINE EXTENSION TO AN EXISTING THREE TURBINE WINDFARM. THE MAXIMUM HUB HEIGHT WILL BE 68.3M AND THE MAXIMUM ROTOR DIAMETER WILL BE 82.4M RESULTING IN A MAXIMUM TIP HEIGHT OF 109.5. THE ASSOCIATED WORKS WILL INCLUDE A TURBINE FOUNDATION, TRANSFORMER AND DRAINAGE, APPLYING FOR 10 YEARS
Development Address:
CLYDAGHROE, CLONKEEN, CO KERRY
Architect Name:
R
Location Key:
CLYDAGHROE
Electoral Division:
Glanlea
Planner:
T J Mahoney
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
MAIN FILE COLOUR GREEN WITH EIS IN WIDE BOX
Decision
Decision Date:
23/02/2011
Manager Order:
Decision Type:
Refused
Number of Conditions:
1
Grant Date:
21/07/2011
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
20/07/2016
Decision Description:
CONSTRUCTION OF A SINGLE TURBINE EXTENSION TO AN EXISTING THREE TURBINE WINDFARM. THE MAXIMUM HUB HEIGHT WILL BE 68.3M AND THE MAXIMUM ROTOR DIAMETER WILL BE 82.4M RESULTING IN A MAXIMUM TIP HEIGHT OF 109.5. THE ASSOCIATED WORKS WILL INCLUDE A TURBINE FOUNDATION, TRANSFORMER AND DRAINAGE, APPLYING FOR 10 YEARS
DEVELOPMENT OF A WIND FARM, THE WIND FARM WILL CONSIST OF 2 WIND TURBINES AND SERVICE ROADWAYS ON A SITE, (AN EIS HAS BEEN SUBMITTED WITH THIS APPLICATION)
DEVELOPMENT UNDERTAKEN AT TURBINE 19. THE DEVELOPMENT CONSISTED OF WORKS THAT INVOLVED STRIPPING A 500M LAYER OF PEAT FROM THE LAND BANK AND DISPOSING OFF SITE. THE SUBSOIL WAS THEN REGARDED FROM A GRADIENT OF 1:1 TO A GRADIENT OF 1:1:5.
CONSTRUCT A WIND FARM TOGETHER WITH ANCILLARY SITE WORKS COMPRISING OF 17 NO TURBINES,SUBSTATION/CONTROL CENTRE BUILDING AND COMPOUND AND SITE ROADS FOR WHICH AN E.I.S HAS BEEN SUBMITTED FOR INSPECTION