Planning Application: 17374 (Louth County Council )
File Number:
17374
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
18/05/2017
Decision Due Date:
07/11/2017
Validated Date:
18/05/2017
Invalidated Date:
Further Info Requested:
04/07/2017
Further Info Received:
11/10/2017
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
27/10/2017
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
24/10/2017
Applicant Details
Applicant name:
Lorna Neary & Niall Conlon
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
Permission for a two storey dwelling house, domestic garage, new vehicular entrance, waste water treatment sytem and associated site development works.
Development Address:
Toomes, Louth , Co Louth
Architect Name:
Location Key:
TOOMES LOUTH, DUNDALK
Electoral Division:
Planner:
Ciara Doran
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
27/10/2017
Manager Order:
813/17
Decision Type:
Conditional
Number of Conditions:
6
Grant Date:
27/11/2017
Grant Managers Order #:
813/17
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
26/11/2022
Decision Description:
Permission for a two storey dwelling house, domestic garage, new vehicular entrance, waste water treatment sytem and associated site development works.
Permission for a 10 year planning permission for the construction of: A solar PV and battery energy storage system development on a c.42.23ha site, consisting of: 1. New site entrance, internal access and entrances and associated works; 2. Solar panels on ground-mounted frames over an area of c.39.98ha, 15 no. single storey electrical inverter/transformer units, security fencing, CCTV system with pole mounted cameras and landscaping; 3. An enclosed batter energy storage compound on c0.758ha consisting of 48 no. battery storage units (each with associated containerised step-up transformer); 1 no. containerised control room, 1 no. containerised switch room and 1 no. containerised switch gear unit. 4. 2 no. 37kv sub-stations each with an IPP building on c.1.4887ha; one serving the solar PV development, the other serving the battery storage system development. 5. 2 no. grid connections to Louth (Monvallet) 275kv substation; 6. A temporary construction compound; and 7. All associated ancillary development works. The operational lifespan of the solar PV and battery energy storage system development will be 35 years. A Natura Impact Statement will accompany the application
No Environment Impact Assesments Associated with this Application