to amend the lifetime of the approved development (Planning ref: LB/160898) which comprises consent for the development of a solar farm on a site of approximately 131.37 hectares consisting of the following: solar photovoltaic panels on ground mounted steel frames, IPP electrical control building and associated compound, inverter/transformer stations, battery storage units and associated hard standings, storage containers for spare parts, underground power and communication cables and ducts, boundary security fencing, upgraded internal access tracks, new internal access tracks and associated drainage infrastructure, CCTV cameras and all associated site services and works at Garballagh, Thomastown, Gillinstown, Duleek, Co Meath subject to 14 conditions. Permission is sought to amend the operational lifespan of the consented development from 25 years to 35 years
Development Address:
Garballagh, Thomastown, Gillinstown, Duleek, Co Meath
Architect Name:
Location Key:
GARBALLAGH
Electoral Division:
Incorrect Icl Voter Recor
Planner:
Kathryn Hosey
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
35yrs applies to operational timeline and not expiry date
Decision
Decision Date:
22/04/2022
Manager Order:
752/22
Decision Type:
Conditional
Number of Conditions:
3
Grant Date:
08/06/2022
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
07/06/2027
Decision Description:
to amend the lifetime of the approved development (Planning ref: LB/160898) which comprises consent for the development of a solar farm on a site of approximately 131.37 hectares consisting of the following: solar photovoltaic panels on ground mounted steel frames, IPP electrical control building and associated compound, inverter/transformer stations, battery storage units and associated hard standings, storage containers for spare parts, underground power and communication cables and ducts, boundary security fencing, upgraded internal access tracks, new internal access tracks and associated drainage infrastructure, CCTV cameras and all associated site services and works at Garballagh, Thomastown, Gillinstown, Duleek, Co Meath subject to 14 conditions. Permission is sought to amend the operational lifespan of the consented development from 25 years to 35 years
Garballagh, Thomastown, Gillinstown and Downestown Duleek Co. Meath
the development will consist of a permission for a period of 10 years to construct and complete the development of a Solar PV Energy development with a total site area of 150.29 hectares, to include two electrical substation buildings and associated compounds, electrical transformer and inverter station modules, storage modules, Solar PV panels ground mounted on support structures, access roads and internal access tracks, spare parts storage container, fencing, electrical cabling and ducting, including undergrounding of existing electrical cabling, CCTV and other ancillary infrastructure, additional landscaping and habitat enhancement as required and associated site development works. Significant Further Information/Revised plans submitted on this application
No Environment Impact Assesments Associated with this Application