Planning application details ref: 2561010 Meath CoCo

100%100% Complete (warning)

Planning Application: 2561010 (Meath CoCo)
File Number: 2561010
Application Type: PERMISSION Planning Status: APPEALED
Received Date: 24/09/2025 Decision Due Date: 03/08/2026
Validated Date: 31/10/2025 Invalidated Date:
Further Info Requested: 19/12/2025 Further Info Received: 09/06/2026
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 30/07/2026
Leave to Appeal: Appeal Date: 26/08/2026
Commenced Date: Submissions By: 13/07/2026

Applicant Details

Applicant name: Circal Oak Solar Limited
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: RED III - The Proposed Development comprises the following – • Construction and operation of up to 559,033 sqm of solar PV arrays on ground-mounted metal frames, with a maximum overall height of up to 2.96 metres. • Internal underground trenching, electrical cabling and ducting between the solar PV arrays and electrical invertor / transformer skid units. • Up to 21 no. electrical inverter / transformer skid units. • Construction and operational access to the site by 3 no. site entrances using 2 no. existing field access points 1 no. new access point. • 3 no. temporary construction compound and ancillary facilities for the duration of the construction phase of the project. • Provision of single storey substation control building of 217 sqm and associated works. • 33kV collector cable network, joint bays and associated works. • Internal access tracks, site landscaping and drainage works, security fencing, CCTV and all associated ancillary site development works. • The decommissioning and reinstatement of the solar farm at the end of its operational life. A 10-year planning permission and a 40-year operational life from the date of commissioning of the entire solar farm is being sought. A Natura Impact Statement (NIS) has been prepared and accompanies the planning application. The NIS assesses both the construction and operation of the Proposed Development, as well as integral elements of the wider project infrastructure, comprising the construction and operation of a 110kV substation compound, control building, 110kV transformer, 110kV cabling, joint bays, future grid connection and associated works (located in the townlands of Rathcoon, Kilberry, Castletown Kilberry, and Silloge), all of which are essential infrastructure associated with the operation of the Proposed Development and will be the subject of a separate, future SID planning application to the relevant consenting authority. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413) [X] YES [ ] NO. The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended.
Development Address: townlands of Chamberstown, Scottstown, Shalvanstown, Mullagha, Rathcoon, and Corballis, County Meath
Architect Name: Location Key: CORBALLIS
Electoral Division: Planner: Michael McKenna
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments: NIS not EIAR

Decision

Decision Date: 30/07/2026 Manager Order: 1262/26
Decision Type: Conditional Number of Conditions: 22
Grant Date: Grant Managers Order #:
Section 47 Apply?: No Part 5 Apply?: No
Expiry Date:
Decision Description: RED III - The Proposed Development comprises the following – • Construction and operation of up to 559,033 sqm of solar PV arrays on ground-mounted metal frames, with a maximum overall height of up to 2.96 metres. • Internal underground trenching, electrical cabling and ducting between the solar PV arrays and electrical invertor / transformer skid units. • Up to 21 no. electrical inverter / transformer skid units. • Construction and operational access to the site by 3 no. site entrances using 2 no. existing field access points 1 no. new access point. • 3 no. temporary construction compound and ancillary facilities for the duration of the construction phase of the project. • Provision of single storey substation control building of 217 sqm and associated works. • 33kV collector cable network, joint bays and associated works. • Internal access tracks, site landscaping and drainage works, security fencing, CCTV and all associated ancillary site development works. • The decommissioning and reinstatement of the solar farm at the end of its operational life. A 10-year planning permission and a 40-year operational life from the date of commissioning of the entire solar farm is being sought. A Natura Impact Statement (NIS) has been prepared and accompanies the planning application. The NIS assesses both the construction and operation of the Proposed Development, as well as integral elements of the wider project infrastructure, comprising the construction and operation of a 110kV substation compound, control building, 110kV transformer, 110kV cabling, joint bays, future grid connection and associated works (located in the townlands of Rathcoon, Kilberry, Castletown Kilberry, and Silloge), all of which are essential infrastructure associated with the operation of the Proposed Development and will be the subject of a separate, future SID planning application to the relevant consenting authority. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413) [X] YES [ ] NO. The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended.

Appeal Details


Appeal Details
Notification Date: 28/08/2026 BP Reference #: PL-501976-MH-26
Appeal Type: THIRD PARTY File Forward Date:
Submission Due Date: 24/09/2026 Submission Sent Date: 15/09/2026
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: