Planning application details ref: AA190803 Meath CoCo

100%100% Complete (warning)

Planning Application: AA190803 (Meath CoCo)
File Number: AA190803
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 19/06/2019 Decision Due Date: 13/08/2019
Validated Date: 19/06/2019 Invalidated Date:
Further Info Requested: Further Info Received:
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 09/08/2019
Leave to Appeal: Appeal Date:
Commenced Date: Submissions By: 23/07/2019

Applicant Details

Applicant name: Dublin Aerospace
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: demolition of existing pumphouse associated with the disused sprinkler system located in the south eastern corner of the site, demolition of existing ESB substation and the erection of a new larger 35 sq.m substation, provision of steel roofed structure to cover the existing bunded area located on the south western boundary, provision of a new HGV reduced level loading bay along gridline H on south eastern elevation, a 30 sq. m compressor room and air handling unit located adjacent to the compresser room at ground floor level on the south eastern elevation between gridlines 3,6/H. Provision of a lean-to pallet storage area between gridlines HL/3 and the location of a waste compactor unit at the end of the lean-to adjacent to L/3. Provision of a new 83 space carpark and associated new entrance roadway and security barriers including wire mesh fencing and gateways on the south eastern corner of the site. Provision of HGV loading door and roller shutter on the eastern elevation along gridline L. Provision of a smoking shelter at the junction of gridlines 6/H. Provision of a bike storage area adjacent gridline 8/2. Demolition of an existing raised roof area between gridlines EF/4, and provision of a raised roof area (3.6m above existing roof level) to accommodate internal craneage between gridlines EF/3.5,5.5, there will be 2 number Air handling units located on top of this raised roof projection. Further provision of a raised roof area to accommodate internal craneage between IL/1,3, there will be one number Air handling unit located on top of this roof. Provision of new external cladding to all areas where cladding exists already, provision of 27 new slit windows 4.5m wide by .8m high to provide high level lighting on the wall elevations of the factory both at high level and on the raised roof projections at high level, all located on main existing factory wall elevations and new roof projections. Replacement of all windows in the current administration block between gridlines AB/2,6 Provision of van loading bays between E, G/6. Provision of two wall mounted signs 33 sq. m in area, provision of water attenuation tanks under the carpark located in the north western corner of the site and also on the northern boundary to connect into existing surface water drain in the north west corner of the site, removal of existing water tanks from the corner of the building adjacent to gridlines 6/B. provision of a new fire escape door and steps along gridline 3.
Development Address: Ashbourne Industrial Estate, Ashbourne, Co. Meath
Architect Name: Keenan Lynch Architects Location Key: COOKSTOWN
Electoral Division: Incorrect Icl Voter Recor Planner: Billy Joe Padden
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 09/08/2019 Manager Order: A1222/19
Decision Type: Conditional Number of Conditions: 16
Grant Date: 23/09/2019 Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 22/09/2024
Decision Description: demolition of existing pumphouse associated with the disused sprinkler system located in the south eastern corner of the site, demolition of existing ESB substation and the erection of a new larger 35 sq.m substation, provision of steel roofed structure to cover the existing bunded area located on the south western boundary, provision of a new HGV reduced level loading bay along gridline H on south eastern elevation, a 30 sq. m compressor room and air handling unit located adjacent to the compresser room at ground floor level on the south eastern elevation between gridlines 3,6/H. Provision of a lean-to pallet storage area between gridlines HL/3 and the location of a waste compactor unit at the end of the lean-to adjacent to L/3. Provision of a new 83 space carpark and associated new entrance roadway and security barriers including wire mesh fencing and gateways on the south eastern corner of the site. Provision of HGV loading door and roller shutter on the eastern elevation along gridline L. Provision of a smoking shelter at the junction of gridlines 6/H. Provision of a bike storage area adjacent gridline 8/2. Demolition of an existing raised roof area between gridlines EF/4, and provision of a raised roof area (3.6m above existing roof level) to accommodate internal craneage between gridlines EF/3.5,5.5, there will be 2 number Air handling units located on top of this raised roof projection. Further provision of a raised roof area to accommodate internal craneage between IL/1,3, there will be one number Air handling unit located on top of this roof. Provision of new external cladding to all areas where cladding exists already, provision of 27 new slit windows 4.5m wide by .8m high to provide high level lighting on the wall elevations of the factory both at high level and on the raised roof projections at high level, all located on main existing factory wall elevations and new roof projections. Replacement of all windows in the current administration block between gridlines AB/2,6 Provision of van loading bays between E, G/6. Provision of two wall mounted signs 33 sq. m in area, provision of water attenuation tanks under the carpark located in the north western corner of the site and also on the northern boundary to connect into existing surface water drain in the north west corner of the site, removal of existing water tanks from the corner of the building adjacent to gridlines 6/B. provision of a new fire escape door and steps along gridline 3.

Appeal Details


Appeal Details
Notification Date: BP Reference #:
Appeal Type: File Forward Date:
Submission Due Date: Submission Sent Date:
Appeal Decision: Decision Date:
Withdrawn Date: Dismissed Date:
Reason: