the erection of 6 Number flood lighting columns each 20m in height around the existing playing pitch and 4 number flood lighting columns each 18m in height around the existing training pitch
demolition of existing sub-standard dressing rooms & for erection of new dressing rooms, shower rooms, meeting rooms with new pitched roof over & for replacement of roof sheeting over main hall with new sheeting to match new roof
the decommissioning/removal of the existing 4 No. 15m high timber floodlighting poles and floodlighting at the main pitch, the erection of 6 No. 18m high lighting masts & floodlighting around the existing playing pitch, the retention of the existing 4 No. 10m high lighting & floodlighting around the existing training pitch, the construction of a 2.0m wide walkway and a 1.2m high perimeter fence around the main pitch, the construction of a 5.0m high ball wall with 14m x 50m all weather playing surface surrounded by 3.0 high mesh fencing and all associated works
No Environment Impact Assesments Associated with this Application