construct a new all weather artificial training pitch within part of the existing car park area together with associated site works including erection of lighting and fencing to training pitch; works will also include the relocation of main entrance gate towards south west corner of the site and the provision of additional car parking at the northern end fo the existing pitch including hardstanding to carpark areas and other associated site works. Further information/revised plans submitted
Development Address:
Ringlestown, Kilmessan, Co Meath
Architect Name:
Location Key:
RINGLESTOWN
Electoral Division:
Kilmessan - Part of
Planner:
Donal Farrelly
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
18/06/2008
Manager Order:
T735/08
Decision Type:
Conditional
Number of Conditions:
7
Grant Date:
23/07/2008
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
22/07/2013
Decision Description:
construct a new all weather artificial training pitch within part of the existing car park area together with associated site works including erection of lighting and fencing to training pitch; works will also include the relocation of main entrance gate towards south west corner of the site and the provision of additional car parking at the northern end fo the existing pitch including hardstanding to carpark areas and other associated site works. Further information/revised plans submitted
Kilmessan Hurling Club Ringlestown, Kilmessan Co. Meath
development will consist of 1) Construction of a proposed new hurling training pitch. 2) Extending of existing playing pitch including moving goal posts and goal stops. 3) Construction of new perimeter fencing to main pitch. 4) Construction of a new 2m wide walking track around the extents of the two pitches. 5) Erection of flood lighting to training pitch. 6) Erection of lighting to walking track. 7) Demolition of storage shed. 8) All ancillary site development works.
No Environment Impact Assesments Associated with this Application