Planning application details ref: ra191593 Meath CoCo

100%100% Complete (warning)

Planning Application: ra191593 (Meath CoCo)
File Number: ra191593
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 27/11/2019 Decision Due Date: 21/06/2020
Validated Date: 27/11/2019 Invalidated Date:
Further Info Requested: 28/01/2020 Further Info Received: 25/02/2020
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 17/06/2020
Leave to Appeal: Appeal Date: 13/07/2020
Commenced Date: Submissions By: 31/05/2020

Applicant Details

Applicant name: EngineNode Ltd
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: the development being applied for consists of the following to be constructed in a minimum of four phases: The construction of 4 number 2 storey data storage buildings with a combined gross floor area of c. 92, 172 sq.m, associated single storey energy centre with a gross floor area of c. 8,906 sq.m with an ancillary 1 storey MV operations building with part basement with a gross floor area of c. 1,016 sq.m, EngineNode 2 storey offices with a gross floor area of 736 sq.m. The data storage campus shall comprise of the following uses: offices, canteen, computer and associated support areas, electrical component rooms, plant and associated equipment. Each Data Storage building includes for a total of 18 number 21.5 m high back-up generator exhaust flues which are incorporated on to the building facade. The energy centre shall comprise of: gas engines, ancillary plant and associate equipment. Each Data Storage building includes for a total of 18 number 21.5m high back-up generator exhaust flues which are incorporated on to the building facde. The energy centre shall comprise of: gas engines, ancillary plant and associate equipment. The energy centre includes for 4 number 40m high x 5m diameter exhaust flues and a standby diesel generator with a 22m high exhaust flue. An IE Licence is required for under the First Schedule of the EPA Act 1992 as amended under "Activity 2.1 Combustion of fuels in installations with a total rated thermal input of 50MW or more". Ancillary facilities on site include for an Above Ground Installation for gas connection, and a temporary ESB MV Substation with gross floor area of 40 sq.m in support of this development. Included in this application are all associated storage tanks, flues, access roads, services, entrance gates, railings, perimeter fencing at 3m high, landscaping and infrastructure inclusive of 245 No. car parking spaces and 3 number attenuation retention ponds. An Environmental Impact Assesment Report (EIAR) has been submitted with this application. Significant further information/revised plans submitted on this application
Development Address: Bracetown & Gunnocks , To the North Of Clonee, Co. Meath
Architect Name: Laurence McCrudden/Peter Fagan Location Key: BRACETOWN
Electoral Division: Incorrect Icl Voter Recor Planner: Billy Joe Padden
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 17/06/2020 Manager Order: R789/20
Decision Type: Conditional Number of Conditions: 23
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 04/07/2031
Decision Description: the development being applied for consists of the following to be constructed in a minimum of four phases: The construction of 4 number 2 storey data storage buildings with a combined gross floor area of c. 92, 172 sq.m, associated single storey energy centre with a gross floor area of c. 8,906 sq.m with an ancillary 1 storey MV operations building with part basement with a gross floor area of c. 1,016 sq.m, EngineNode 2 storey offices with a gross floor area of 736 sq.m. The data storage campus shall comprise of the following uses: offices, canteen, computer and associated support areas, electrical component rooms, plant and associated equipment. Each Data Storage building includes for a total of 18 number 21.5 m high back-up generator exhaust flues which are incorporated on to the building facade. The energy centre shall comprise of: gas engines, ancillary plant and associate equipment. Each Data Storage building includes for a total of 18 number 21.5m high back-up generator exhaust flues which are incorporated on to the building facde. The energy centre shall comprise of: gas engines, ancillary plant and associate equipment. The energy centre includes for 4 number 40m high x 5m diameter exhaust flues and a standby diesel generator with a 22m high exhaust flue. An IE Licence is required for under the First Schedule of the EPA Act 1992 as amended under "Activity 2.1 Combustion of fuels in installations with a total rated thermal input of 50MW or more". Ancillary facilities on site include for an Above Ground Installation for gas connection, and a temporary ESB MV Substation with gross floor area of 40 sq.m in support of this development. Included in this application are all associated storage tanks, flues, access roads, services, entrance gates, railings, perimeter fencing at 3m high, landscaping and infrastructure inclusive of 245 No. car parking spaces and 3 number attenuation retention ponds. An Environmental Impact Assesment Report (EIAR) has been submitted with this application. Significant further information/revised plans submitted on this application

Appeal Details


Appeal Details
Notification Date: 17/07/2020 BP Reference #: ABP 307546-20
Appeal Type: THIRD PARTY File Forward Date: 31/07/2020
Submission Due Date: 21/09/2020 Submission Sent Date: 17/09/2020
Appeal Decision: MODIFIED Decision Date: 05/07/2021
Withdrawn Date: Dismissed Date:
Reason: