The development will consist of a three-storey office unit to include staff facility areas for canteen toilets, locker rooms ,also to include
shelf life test area and reception area to rear of existing vegtable store, to remove pre-fabricated units, to install an Oakstown BAF wastewater treatment system and to retain storage /packing area to rear of premises(previously in open yard area),
and primary treatment and storage unit for potatowash water
Development Address:
Braystown, Lobinstown, Navan, Co Meath
Architect Name:
Location Key:
LOBINSTOWN
Electoral Division:
Killary - Part of
Planner:
Turlough King
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
24/10/2007
Manager Order:
S4363/07
Decision Type:
Refused
Number of Conditions:
4
Grant Date:
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
24/10/2012
Decision Description:
The development will consist of a three-storey office unit to include staff facility areas for canteen toilets, locker rooms ,also to include
shelf life test area and reception area to rear of existing vegtable store, to remove pre-fabricated units, to install an Oakstown BAF wastewater treatment system and to retain storage /packing area to rear of premises(previously in open yard area),
and primary treatment and storage unit for potatowash water
to erect a 300kw wind turbine 30m high with a blade diameter of 30m, a new access roadway connecting to existing private roadway with underground ducting connecting to existing ESB Substation and all associated site works