Planning application details ref: 18562 Monaghan County Council

100%100% Complete (warning)

Planning Application: 18562 (Monaghan County Council )
File Number: 18562
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 04/12/2018 Decision Due Date: 04/09/2019
Validated Date: 04/12/2018 Invalidated Date:
Further Info Requested: 06/02/2019 Further Info Received: 11/07/2019
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 04/09/2019
Leave to Appeal: Appeal Date: 01/10/2019
Commenced Date: Submissions By: 14/08/2019

Applicant Details

Applicant name: Coolberrin Wind Limited
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: permission for the construction of a 38kv electricity substation, switchroom and equipment compound with palisade fence; the construction of approximately 400m of site access track and the upgrading of approximately 150m of existing agricultural track and an existing agricultural site entrance; approximately 200m of underground cabling and all associated site development and reinstatement works in the townland of Luppan, County Monaghan; and (ii) the installation of approximately 22km of 38kV electricity cables from the proposed substation to the existing electricity substation in the townland of Lisdrumdoagh, County Monaghan. The electricity cables will comprise approximately 17km of overhead line and approximately 5 km of underground line. Overhead lines will consist of 3 no. cables suspended from wooden poles with a maximum height of 16 metres, and all associated site development and reinstatement works. Underground cables will be located within private lands and within the public roads numbered L5171, L1400 and L1171; will be installed in excavated trenches of approximately 1.2m in depth and will include associated underground ducting, joint bays, communication chamber bays, sheath link boxes and inspection chambers; directional drilling beneath the N12 and Ulster Canal and all associated site development and reinstatement works. A vehicle access track of up to 4m in width will be provided immediately adjacent to underground cables with private lands. This planning application is accompanied by an Environmental Impact Assessment Report which includes an assessment of the likely impacts of the proposed development, as a whole and in combination with the relevant off-site or secondary developments which will occur as a direct result of the proposed development, including the wind farm development permitted pursuant to Monaghan County Council Planning Register Reference 10/110 & An Bord Pleanála Reference PL18.240760 and proposed to be amended by planning reference 17/258 & An Bord Pleanála Reference PL18.300998 (currently under construction). A Natura Impact Statement will also be submitted to the planning authority with the planning application. This application is accompanied by an EIAR. Significant Further information has been submitted.
Development Address: Luppan, County Monaghan and across the townlands of Shanmullagh, Coraghbrack, Drumlester, Knockabeany, Drumbristan, Tonintlieve, Cloghfin, Derrykinnigh More, Killybreen, Killycarran, Derrygola, Tamlet, Derrilla, Tonyfinnigan, Knockcor, Drumdart, Agha
Architect Name: Conor Harty & Cormac McPhillips Location Key: LUPPAN
Electoral Division: Planner: Helen McCourt
Social Housing Exempt: Plan Enforcement #:
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Comments:

Decision

Decision Date: 04/09/2019 Manager Order: P959/19
Decision Type: Conditional Number of Conditions: 17
Downloads a Microsoft Word Document (Document Size 35 Kb)

Download a Free Word viewer
Grant Date: Grant Managers Order #:
Section 47 Apply?: Part 5 Apply?:
Expiry Date: 29/06/2028
Decision Description: permission for the construction of a 38kv electricity substation, switchroom and equipment compound with palisade fence; the construction of approximately 400m of site access track and the upgrading of approximately 150m of existing agricultural track and an existing agricultural site entrance; approximately 200m of underground cabling and all associated site development and reinstatement works in the townland of Luppan, County Monaghan; and (ii) the installation of approximately 22km of 38kV electricity cables from the proposed substation to the existing electricity substation in the townland of Lisdrumdoagh, County Monaghan. The electricity cables will comprise approximately 17km of overhead line and approximately 5 km of underground line. Overhead lines will consist of 3 no. cables suspended from wooden poles with a maximum height of 16 metres, and all associated site development and reinstatement works. Underground cables will be located within private lands and within the public roads numbered L5171, L1400 and L1171; will be installed in excavated trenches of approximately 1.2m in depth and will include associated underground ducting, joint bays, communication chamber bays, sheath link boxes and inspection chambers; directional drilling beneath the N12 and Ulster Canal and all associated site development and reinstatement works. A vehicle access track of up to 4m in width will be provided immediately adjacent to underground cables with private lands. This planning application is accompanied by an Environmental Impact Assessment Report which includes an assessment of the likely impacts of the proposed development, as a whole and in combination with the relevant off-site or secondary developments which will occur as a direct result of the proposed development, including the wind farm development permitted pursuant to Monaghan County Council Planning Register Reference 10/110 & An Bord Pleanála Reference PL18.240760 and proposed to be amended by planning reference 17/258 & An Bord Pleanála Reference PL18.300998 (currently under construction). A Natura Impact Statement will also be submitted to the planning authority with the planning application. This application is accompanied by an EIAR. Significant Further information has been submitted.

Appeal Details


Appeal Details
Notification Date: 20/04/2021 BP Reference #: ABP-309906-21
Appeal Type: THIRD PARTY File Forward Date: 10/10/2019
Submission Due Date: 17/05/2021 Submission Sent Date:
Appeal Decision: CONDITIONAL Decision Date: 30/06/2023
Withdrawn Date: Dismissed Date:
Reason: