Planning Application: 08393 (Roscommon County Council )
File Number:
08393
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
01/04/2008
Decision Due Date:
07/09/2008
Validated Date:
01/04/2008
Invalidated Date:
Further Info Requested:
16/05/2008
Further Info Received:
11/08/2008
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
05/09/2008
Leave to Appeal:
Appeal Date:
01/10/2008
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Roadstone Provinces Ltd.,
Applicant Address:
Phone Number:
Fax Number:
091 752199
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
For the installation and operation of an asphalt plant and ancillary facilities (including bitumen storage tanks) on 1.46 hectares of land within the existing quarry and concrete manufacturing site (Planning Ref. No. 04/1479). The overall height of the plant will be 28.35 metres above site level of 86mOD at
For the installation and operation of an asphalt plant and ancillary facilities (including bitumen storage tanks) on 1.46 hectares of land within the existing quarry and concrete manufacturing site (Planning Ref. No. 04/1479). The overall height of the plant will be 28.35 metres above site level of 86mOD at
For development of a quarry on c.68 hectares of lands, of which c.23.7 hectares is the extraction area. The proposed development is for extraction of limestone using conventional blasting techniques and processing of rock using crushing and screening plant. The proposal also includes for provision of a concrete block making facility and concrete batching plant, a truck washdown facility with wash water recycled via a closed settlement tank system, the storage of aggregates, ESB substation (26m2), portacabin office facilities including canteen and washroom facilities (91m2), a workshop including storage room, canteen and washroom (485m2), septic tank and percolation area, bunded fuel storage area, vehicle circulation/access including wheelwash and weighbridge, settlement tanks/hydrocarbon interceptors for treatment of water, construction of overburden and screening mounds, all other associated site works and ancillary activities, This application is accompanied by an Environmental Impact Statement (EIS) at
No Environment Impact Assesments Associated with this Application