Planning Application: 22323 (Roscommon County Council )
File Number:
22323
Application Type:
PERMISSION
Planning Status:
INCOMPLETED APPLICATION
Received Date:
28/06/2022
Decision Due Date:
Validated Date:
Invalidated Date:
28/06/2022
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Decision Date:
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
01/08/2022
Applicant Details
Applicant name:
Peter Gillooly,
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
Permission for (A) amendments to (i) extant planning permission PD/18/313, which amended planning application PD/11/126, (ii) extant planning permission ABP-303677-19, which amended planning permissions PD/11/126 and PD/18/313 and (iii) extant planning permission ABP-307726-20, which amended planning permission PD/18/313. (B) Permission for the development of a battery storage unit and a transformer unit. The amendments in (A) above will provide for : 1. Erection of two Enercon E138 turbine models in lieu of the Vensys 121 turbine models agreed with the Planning Authority, under condition 4(a) of planning permission ABP-3037726-19. Turbine T1 will have a hub height of 95.53m, a blade diameter of 138m and a blade tip height of 164.65m. Turbine T2 will have a hub height of 81m and blade diameter of 138m and a blade tip height of 150m. The combined output from the turbines will be 4.9MW. 2. Relocation of the access road serving the development, as previously permitted under planning permissions PD/11/126, PD/18/313, ABP-303677-49 and ABP-307726-20, 3. The relocation of underground electrical cabling to the relocated access road referred to under paragraph 2 above and additional underground electrical cabling to serve the proposed modular windfarm control and switch rooms, the ESB modular MV station referred to in paragraph 6 below and the new battery storage and transformer units referred to in (B) above, 4. Increase in the hub height of turbine T1 to 95.53m, increasing the blade tip height from 150m to 164.65m and mocro-siting of turbine T1 by 12.75m. 5. Increase in the area of the hardstands associated with each turbine, 6. Amended substation structure to incorporate a proposed modular windfarm control from and switch rooms and ESB modular MV station, 7. Revised site boundaries at
Permission for: (A) amendments to (i) extant planning permission PD/18/313, which amended planning application PD/11/126, (ii) extant planning permission ABP-303677-19, which amended planning permissions PD/11/126 and PD/18/313 and (iii) extant planning permission ABP-307726-20, which amended planning permission PD/18/313; (B) Permission for the development of a battery storage unit and a transformer unit. The amendments in (A) above will provide for : 1. Erection of two Enercon E138 turbine models in lieu of the Vensys 121 turbine models agreed with the Planning Authority, under condition 4(a) of planning permission ABP-3037726-19. Turbine T1 will have a hub height of 95.53m, a blade diameter of 138m and a blade tip height of 164.65m. Turbine T2 will have a hub height of 81m and blade diameter of 138m and a blade tip height of 150m. The combined output from the turbines will be 4.9MW; 2. Relocation of the access road serving the development, as previously permitted under planning permissions PD/11/126, PD/18/313, ABP-303677-19 and ABP-307726-20; 3. The relocation of underground electrical cabling to the relocated access road referred to under paragraph 2 above and additional underground electrical cabling to serve the proposed modular windfarm control and switch rooms, the ESB modular MV station, referred to in paragraph 6 below and the new battery storage and transformer units referred to in (B) above; 4. Increase in the hub height of turbine T1 to 95.53m, increasing the blade tip height from 150m to 164.65m and micro-siting of turbine T1 by 12.75m; 5. Increase in the area of the hardstands associated with each turbine; 6. Amended substation structure to incorporate a proposed modular windfarm control and switch rooms and an ESB modular MV station; 7. Revised site boundaries at
Permission for amendments to (i) extant planning permission PD18/313, which amended planning application PD/11/126, (ii) extant planning permission ABP-303677-19, which amended planning permissions PD11/126 and PD18/313 and (iii) extant planning permission ABP-307726-20, which amended planning permission PD18/313. The output from the development will be 4.9MW, similar to the extant planning permissions. The amendments will provide for
1. Erection of two bespoke Enercon E138 turbines models in lieu of the Vensys 121 turbine models agreed with the Planning Authority, under condition 4(a) of planning permission ABP-3037726-19. Turbine T1 will have a hub height of 99m, a blade diameter of 138m and a blade tip height of 168m.Turbine T2 will have a hub height of 81m, a blade diameter of 138m and a blade tip height of 150m. The maximum combined output from the turbines will be 4.9MW.
2. Relocation of the access road serving the development, as permitted under planning permissions PD11/126, PD18/313, ABP-303677-19 and ABP-307726-20.
3. The relocation of underground electrical cabling to the relocated access road referred to under paragraph 2 above and additional underground electrical cabling to the proposed modular windfarm control room/switch room and ESB modular MV station referred to in paragraph 6 below.
4. Increase in the hub height of turbine T1 to 99m, increasing the blade tip height from 150m to 168m and micro-siting of turbine T1 by 12.75m.
5. Increase in the area of the hardstands associated with each turbine.
6. Amended substation structure to incorporate a proposed modular windfarm control/switch rooms and an ESB modular MV station.
7. Revised site boundaries at
No Environment Impact Assesments Associated with this Application