Planning Application: 04968 (Tipperary County Council )
File Number:
04968
Application Type:
PERMISSION FOR RETENTION
Planning Status:
APPLICATION FINALISED
Received Date:
20/07/2004
Decision Due Date:
29/03/2006
Validated Date:
20/07/2004
Invalidated Date:
Further Info Requested:
13/09/2004
Further Info Received:
02/03/2006
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
29/03/2006
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
Denis Tarrant
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
extension to quarry, retention of office block and ancillary works at the entrance including weighbridge and cabin, retention of the truck repair / maintenance building, retention of the first aid / canteen building and retention of ready mix plant and machinery
extension to quarry, retention of office block and ancillary works at the entrance including weighbridge and cabin, retention of the truck repair / maintenance building, retention of the first aid / canteen building and retention of ready mix plant and machinery
Deerpark, Kilfeacle & Knockballynoe East Townslands Kilfeacle
continued use of previously permitted development under Ref No 04/968 & P.3.8382 & the grant of Substitute Consent Ref SU23.SU0005, including existing quarry, stone extraction & processing, concrete manufacturing facility, & related ancillary buildings & facilities. Permission for extension to existing quarry area by c.8.4h to give an overall extraction footprint of c.17.1h. The final quarry floor level will be similar to that of the existing quarry void, @ c.73mOD. Permission for construction of a new concrete block batching plant & associated production slab measuring 9800m2. Permission for replacement of exisitng septic tank adjacent to weighbridge site office with a proprietary effluent treatment system(new septic tank & modular puraflo). New electricity substation comprising of supplyroom & switchroom. Increase production output from quarry, from 150,000 tonnes pa to 250,000 tonnes pa, in line with market demand & all assoc site works within an overall application area of 32.5h, & all for a period of 25 years. An Environmental Impact Statement has been submitted
No Environment Impact Assesments Associated with this Application