File No |
Staus |
Type |
Decision |
Received Date |
Name |
Development Address |
Description |
16600565 |
APPLICATION FINALISED |
PERMISSION |
C |
20/06/2016 Monday |
Lightsource Renewable Energy Ireland Limited |
Monaraha Cahir Co. Tipperary |
a ten year permission for the construction, operation and decommissioning of a solar photovoltaic panel array to export electricity to the national grid. The proposed works will include a 19.10 MWp solar farm comprising photovoltaic panels on ground mounted frames, 10 no. inverter stations, 1 no. single storey substation, 5 no. field transformer, 1 no. single storey communications building, 1 no. single storey storage shed, 1 no. battery container, 1 no. transformer container, 1 no. WC, fencing, temporary construction compound, access track, CCTV and all associated ancillary development works |
2046 |
APPLICATION FINALISED |
PERMISSION |
C |
22/01/2020 Wednesday |
Lightsource Renewable Energy Ireland Limited |
Monaraha Cahir Co. Tipperary |
amend previously approved planning consent 16/600565 for a grant of a ten-year planning permission for a solar farm, the development will consist of an increase in the previously approved mega wattage output; amendments to the previously approved site layout including a reduced number of overall panel modules; additional and revised battery storage units; additional and revised designs for inverters and field transformers; the inclusion of switchgear substations; revisions to the panel elevations to include bi-facial panels; revisions to the panel dimensions to include an increased panel (and leg) max height of no more than 2.5m; revisions to the individual panel width and length; and a reduction in the spacing between the panel rows. Permission is also sought to extend the operational lifespan of the solar farm from 30 years to 35 years from commissioning to the grid |
21327 |
INCOMPLETED APPLICATION |
PERMISSION |
|
16/03/2021 Tuesday |
Monaraha Solar Farm Limited |
Monaraha Cahir Co. Tipperary |
amend previously approved planning consents (Tipperary County Council Ref 16/600565 and 20/46) for a solar farm. The development will consist of a modification to the previously approved on-site substation to allow for a 38kV electrical substation configuration within the solar farm. In order to facilitate the construction of the 38kV substation design, the previously approved 3 no. battery storage units and approximately 240m" of previously approved PV panel area will be replaced. The 38kV substation will include the construction of a control building, an ESB and IPP compound with associated infrastructure including a 38kV busbar, 38kV transformer, 38kV electrical equipment, lightning mast, and all associated ancillary infrastructure required for the project |
21446 |
APPLICATION FINALISED |
PERMISSION |
C |
07/04/2021 Wednesday |
Monaraha Solar Farm Limited |
Monaraha Cahir Co. Tipperary |
amend previously approved planning consents (Tipperary County Council Ref 16/600565 and 20/46) for a solar farm. The development will consist of a modification to the previously approved on-site substation to allow for a 38kV electrical substation configuration within the solar farm. In order to facilitate the construction of the 38kV substation design, the previously approved 3 no. battery storage units and approximately 240m of previously approved PV panel area will be replaced. The 38kV substation will include the construction of a control building, an ESB and IPP compound with associated infrastructure including a 38kV busbar, 38kV transformer, 38kV electrical equipment, lightning mast, and all associated ancillary infrastructure required for the project |
22109 |
INCOMPLETED APPLICATION |
PERMISSION |
|
10/02/2022 Thursday |
Monaraha Solar Farm Ltd |
Monaraha Cahir Co. Tipperary |
proposed development seeks to amend the solar farm permitted on the site under Tipperary County Council Reg. Ref. 16/600565 and Reg. Ref. 20/46 and consists of a revised solar PV panel arrangement resulting in an increase in the overall panel footprint extent; a reconfigured internal access route network resulting in a decrease to the overall network length; the reduction in the number of transformer stations from 16 no. to 5 no. and the provision of string inverters to the rear of panel arrays. It is also proposed to reduce the previously permitted maximum export capacity to 19 MW |
22152 |
APPLICATION FINALISED |
PERMISSION |
C |
23/02/2022 Wednesday |
Monaraha Solar Farm Ltd |
Monaraha Cahir
|
To amend the solar farm permitted on the site under Tipperary County Council Reg. Ref. 20/46 and consists of a revised solar PV panel arrangement resulting in an increase in the overall panel footprint extent; a reconfigured internal – access route network resulting in a decrease to the overall network length; the reduction in the number of transformer stations from 16 No. to 5 No. and the provision of string inverters to the rear of panel arrays. It is also proposed to reduce the previously permitted maximum export capacity to 19 MW. |