Planning application details ref: 1950042 Donegal County Council

100%100% Complete (warning)

Planning Application: 1950042 (Donegal County Council )
File Number: 1950042
Application Type: PERMISSION Planning Status: APPLICATION FINALISED
Received Date: 21/01/2019 Decision Due Date: 23/09/2019
Validated Date: 21/01/2019 Invalidated Date:
Further Info Requested: 15/03/2019 Further Info Received: 21/05/2019
Withdrawn Date: Extend Date:
Decision Type: Conditional Decision Date: 23/09/2019
Leave to Appeal: Appeal Date: 18/10/2019
Commenced Date: Submissions By: 02/09/2019

Applicant Details

Applicant name: GLENMORE GENERATION LTD
Applicant Address:
Phone Number: Fax Number:
Corresp. Address:

Applicant Details


Proposed Development

Development Description: DEVELOPMENT WORKS AT THE GLENMORE BIOGAS PLANT, WHICH SHALL PROCESS ALTERNATIVE FEEDSTOCKS AND PRODUCE RENEWABLE ENERGY AND FERTILISER. THE DEVELOPMENT WILL BE ACCESSED VIA THE EXISTING INTERNAL CONNECTING ACCESS ROAD WITHIN GLENMORE ESTATE WHICH LINKS THE SITE TO THE R253. THE WORKS INVOLVE: (1) DEVELOPMENT WITHIN CURTILAGE OF THE EXISTING BIOGAS PLANT INVOLVING (A) THE CONSTRUCTION/ PROVISION OF AN EXTENSION TO THE EXISTING FEEDSTOCK (WASTE) RECEPTION BUILDING TO ACCOMMODATE FEEDSTOCK RECEPTION ACTIVITIES AND DIGESTATE PROCESSING EQUIPMENT, (B) GAS PURIFICATION AND COMPRESSION PLANT, (C) OFFICE EXTENSION (FIRST FLOOR OPEN PLAN) , AND (D) EXTERNALLY LOCATED TEST TANK; (2) EXTENSION TO THE NORTHERN BOUNDARY OF THE BIOGAS PLANT TO ACCOMMODATE (A) INTERNAL ACCESS ROAD FROM THE EXISTING BIOGAS SITE, (B) CONCRETE RETENTION BUND, (C) 3 NO. DIGESTERS VESSELS WITH COLLECTION DOMES, (D) 3 NO. HYDROLYSIS TANK WITH COLLECTION COVERS, (E) PUMP HOUSES (2 NO.) AND ASSOCIATED PROCESS PIPEWORK, AND (F) STORMWATER ATTENUATION TANK, PETROL INTERCEPTOR AND ASSOCIATED PIPEWORK; (3) EXTENSION TO THE NORTHERN BOUNDARY OF THE BIOGAS PLANT TO ACCOMMODATE A FERTILISER PLANT, COMPRISING (A) FERTILISER PROCESSING BUILDING CONTAINING DIGESTATE PROCESSING EQUIPMENT, STORAGE AREAS AND ASSOCIATED, EXTERNALLY LOCATED, ODOUR CONTROL EQUIPMENT/EXHAUST STACK (17.5M IN HEIGHT), (B) LIQUID FERTILISER STORAGE TANKS (6 NO.), (C) HGV PARKING, (D) ALL PROCESS PIPEWORK AND ASSOCIATED DRAINAGE WORKS, AND (E) ASSOCIATED SITE WORKS INCLUDING FENCING AND LANDSCAPE SCREENING. THE PLANNING APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) AND A NATURA IMPACT STATEMENT (NIS) AND RELATES TO DEVELOPMENT WHICH COMPRISES AN ACTIVITY REQUIRING AN INDUSTRIAL EMISSIONS LICENCE FROM THE ENVIRIONMENTAL PROTECTION AGENCY (EPA)
Development Address: GLENMORE ESTATE , AGHAVEAGH , BALLYBOFEY , LIFFORD PO, CO. DONEGAL
Architect Name: Location Key: AGHAVEAGH
Electoral Division: Altnapaste Planner:
Social Housing Exempt: Plan Enforcement #: UD18276
IPC Licence Required: No Waste Licence Required: No
Protected Structure: No Protected Structure #:
Development Name:

Proposed Development


Comments

Significant Case Flag: Yes Comments:

Decision

Decision Date: 23/09/2019 Manager Order: 2019PH1907
Decision Type: Conditional Number of Conditions: 26
Grant Date: Grant Managers Order #:
Section 47 Apply?: No Part 5 Apply?: No
Expiry Date: 21/09/2026
Decision Description: DEVELOPMENT WORKS AT THE GLENMORE BIOGAS PLANT, WHICH SHALL PROCESS ALTERNATIVE FEEDSTOCKS AND PRODUCE RENEWABLE ENERGY AND FERTILISER. THE DEVELOPMENT WILL BE ACCESSED VIA THE EXISTING INTERNAL CONNECTING ACCESS ROAD WITHIN GLENMORE ESTATE WHICH LINKS THE SITE TO THE R253. THE WORKS INVOLVE: (1) DEVELOPMENT WITHIN CURTILAGE OF THE EXISTING BIOGAS PLANT INVOLVING (A) THE CONSTRUCTION/ PROVISION OF AN EXTENSION TO THE EXISTING FEEDSTOCK (WASTE) RECEPTION BUILDING TO ACCOMMODATE FEEDSTOCK RECEPTION ACTIVITIES AND DIGESTATE PROCESSING EQUIPMENT, (B) GAS PURIFICATION AND COMPRESSION PLANT, (C) OFFICE EXTENSION (FIRST FLOOR OPEN PLAN) , AND (D) EXTERNALLY LOCATED TEST TANK; (2) EXTENSION TO THE NORTHERN BOUNDARY OF THE BIOGAS PLANT TO ACCOMMODATE (A) INTERNAL ACCESS ROAD FROM THE EXISTING BIOGAS SITE, (B) CONCRETE RETENTION BUND, (C) 3 NO. DIGESTERS VESSELS WITH COLLECTION DOMES, (D) 3 NO. HYDROLYSIS TANK WITH COLLECTION COVERS, (E) PUMP HOUSES (2 NO.) AND ASSOCIATED PROCESS PIPEWORK, AND (F) STORMWATER ATTENUATION TANK, PETROL INTERCEPTOR AND ASSOCIATED PIPEWORK; (3) EXTENSION TO THE NORTHERN BOUNDARY OF THE BIOGAS PLANT TO ACCOMMODATE A FERTILISER PLANT, COMPRISING (A) FERTILISER PROCESSING BUILDING CONTAINING DIGESTATE PROCESSING EQUIPMENT, STORAGE AREAS AND ASSOCIATED, EXTERNALLY LOCATED, ODOUR CONTROL EQUIPMENT/EXHAUST STACK (17.5M IN HEIGHT), (B) LIQUID FERTILISER STORAGE TANKS (6 NO.), (C) HGV PARKING, (D) ALL PROCESS PIPEWORK AND ASSOCIATED DRAINAGE WORKS, AND (E) ASSOCIATED SITE WORKS INCLUDING FENCING AND LANDSCAPE SCREENING. THE PLANNING APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) AND A NATURA IMPACT STATEMENT (NIS) AND RELATES TO DEVELOPMENT WHICH COMPRISES AN ACTIVITY REQUIRING AN INDUSTRIAL EMISSIONS LICENCE FROM THE ENVIRIONMENTAL PROTECTION AGENCY (EPA)

Appeal Details


Appeal Details
Notification Date: 22/10/2019 BP Reference #: ABP-305691-19
Appeal Type: THIRD PARTY File Forward Date: 04/11/2019
Submission Due Date: 18/11/2019 Submission Sent Date: 15/11/2019
Appeal Decision: CONDITIONAL Decision Date: 22/09/2021
Withdrawn Date: Dismissed Date:
Reason: