Planning Application: 11270 (Tipperary County Council )
File Number:
11270
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
24/06/2011
Decision Due Date:
18/08/2011
Validated Date:
24/06/2011
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
18/08/2011
Leave to Appeal:
Appeal Date:
13/09/2011
Commenced Date:
Submissions By:
Applicant Details
Applicant name:
ESB Wind Developments Ltd
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
Development consisting of alterations to the existing Cauteen 110kV station comprising of a new 110kV busbar including coupler bay, extension to the existing 110kV busbar, extension to the existing 38kV busbar, two new 110kV line bays, two new transformers and associated transformer bays, extension to the existing control building, existing entrance road and internal road to be extended, existing palisade compound to be extended and associated site works.
Development consisting of alterations to the existing Cauteen 110kV station comprising of a new 110kV busbar including coupler bay, extension to the existing 110kV busbar, extension to the existing 38kV busbar, two new 110kV line bays, two new transformers and associated transformer bays, extension to the existing control building, existing entrance road and internal road to be extended, existing palisade compound to be extended and associated site works.
Development consisting of alterations to the existing Cauteen 110kV station comprising of a new 110kV busbar including coupler bay, extension to the existing 110kV busbar, extension to the existing 38kV busbar, two new 110kV line bays, two new transformers and associated transformer bays, extension to the existing control building, existing entrance road and internal road to be extended, existing palisade compound to be extended and associated site works, previous ref 11/270
ten year planning permission to develop an electricity service, entailing of the laying of a 20kV underground cable from the proposed Inchivara Wind Farm to proposed 38V substation at Graniera and a 38kV underground cable from the proposed 38kV substation at Graniera to the existing Cauteen 110kV/38kV substation at Seskin, Co Tipperary. The proposed development will consist of three phase underground electrical cables laid in ducts, with communications cable, draw pits, jointing bays, cable sheath sectionalising chambers, works to terminus substations and all associated works
No Environment Impact Assesments Associated with this Application