Planning Application: 13510414 (Tipperary County Council )
File Number:
13510414
Application Type:
PERMISSION
Planning Status:
APPLICATION FINALISED
Received Date:
20/12/2013
Decision Due Date:
22/02/2014
Validated Date:
20/12/2013
Invalidated Date:
Further Info Requested:
Further Info Received:
Withdrawn Date:
Extend Date:
Decision Type:
Conditional
Decision Date:
20/02/2014
Leave to Appeal:
Appeal Date:
Commenced Date:
Submissions By:
01/02/2014
Applicant Details
Applicant name:
ABO Wind Ireland Ltd.
Applicant Address:
Phone Number:
Fax Number:
Corresp.
Address:
Applicant Details
Proposed Development
Development Description:
ten year permission and the development will consist of a new entrance (on the R497 regional road) and associated works. This application is part of a separate planning application being made to South Tipperary County Council for a proposed wind energy project comprising two wind turbines (each with a maximum tip height of 126 metres), construction of new internal access roads, upgrading of existing internal access roads, underground cables and associated works in the townlands of Knockduff and Inchivara, South Tipperary. An Environmental Impact Statement and Natura Impact Statement accompany this application
Development Address:
Graniera, Milestone, Co. Tipperary
Architect Name:
Location Key:
GRANIERA, MILESTONE
Electoral Division:
150
Planner:
Feargus Wright
Social Housing Exempt:
Plan Enforcement #:
IPC
Licence Required:
No
Waste Licence Required:
No
Protected Structure:
No
Protected Structure #:
Development Name:
Proposed Development
Comments
Significant Case Flag:
Comments:
Decision
Decision Date:
20/02/2014
Manager Order:
Decision Type:
Conditional
Number of Conditions:
5
Grant Date:
27/03/2014
Grant Managers Order #:
Section 47
Apply?:
Part 5
Apply?:
Expiry Date:
26/03/2024
Decision Description:
ten year permission and the development will consist of a new entrance (on the R497 regional road) and associated works. This application is part of a separate planning application being made to South Tipperary County Council for a proposed wind energy project comprising two wind turbines (each with a maximum tip height of 126 metres), construction of new internal access roads, upgrading of existing internal access roads, underground cables and associated works in the townlands of Knockduff and Inchivara, South Tipperary. An Environmental Impact Statement and Natura Impact Statement accompany this application
ten year planning permission to develop an electricity service, entailing of the laying of a 20kV underground cable from the proposed Inchivara Wind Farm to proposed 38V substation at Graniera and a 38kV underground cable from the proposed 38kV substation at Graniera to the existing Cauteen 110kV/38kV substation at Seskin, Co Tipperary. The proposed development will consist of three phase underground electrical cables laid in ducts, with communications cable, draw pits, jointing bays, cable sheath sectionalising chambers, works to terminus substations and all associated works